Prepared for project use
SKArating Higher Education 1.0 — RIBA Stage 0–6 Programme
When every deliverable, report and exercise has to happen, assuming all 125 in-programme Good Practice Measures are scoped in and targeted. Diamonds mark the stage by which a report or document must be issued to the team in final form — not when the Assessor submits it.
Owner
SKA Assessor
Main contractor
Design team
Technical consultants
Client / university
ActivityActiveOngoingIssued — final documentWorkshop / meetingALLScoped in for all fit-outs
| SKA good practice measures | RIBA plan of work stage | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| Exercise / report / deliverable | SKA GPM refs | Owner | 0Strategic Definition | 1Preparation & Brief | 2Concept Design | 3Spatial Coordination | 4Technical Design | 5Manufacturing & Construction | 6Handover & Close-out |
| Assessment, targeting & project set-up | |||||||||
| Scheme selection & rating targetScheme selection & rating target All GPMs · SKA Assessor (Welscape) SKA Higher Education 1.0, target rating and project boundary confirmed in the client brief.S0 ISSUED |
All GPMs | SKA Assessor | |||||||
| Pre-assessment workshop & GPM scopingPre-assessment workshop & GPM scoping All 131 GPMs · SKA Assessor (Welscape) Workshop the full measure list; issue the scoping & targeting schedule by end of Stage 2. v1 scores against the measures in scope, so scoping decisions drive the rating directly.S1 workshop · S2 ISSUED |
All 131 GPMs | SKA Assessor | |||||||
| Credit target tracker & scoring modelCredit target tracker & scoring model All targeted GPMs · SKA Assessor (Welscape) Live model of in-scope vs achieved measures and the resulting rating band. Maintained from brief to handover.S1 active · S2 ongoing · S3 ongoing · S4 ongoing · S5 ongoing · S6 ISSUED |
All targeted GPMs | SKA Assessor | |||||||
| ALLCCS registration & site monitoringCCS registration & site monitoring D44 · Main contractor / PCSA · scoped in for all fit-outs Considerate Constructors registration written into the contract; monitoring reports and score at handover.S4 ISSUED · S5 ongoing · S6 ISSUED |
D44 | Main contractor | |||||||
| Social value action planSocial value action plan P14 · University estates, client & PM Social, economic and environmental plan committing to four or more criteria. In scope above £2m.S1 active · S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
P14 | Client / university | |||||||
| DESIGN STAGE assessment reportDESIGN STAGE assessment report All targeted GPMs · SKA Assessor (Welscape) Assessor's report on the targeted measures, issued at the end of technical design.S4 ISSUED |
All targeted GPMs | SKA Assessor | |||||||
| Pre-contract & subcontractor SKA briefingsPre-contract & subcontractor SKA briefings D44 · D09 · D60 · D19 · SKA Assessor (Welscape) Walk the contractor and each subcontractor through every targeted measure and its evidence.S4 workshop · S5 workshop |
D44 · D09 · D60 · D19 | SKA Assessor | |||||||
| Site visits & credits-at-risk reportSite visits & credits-at-risk report All targeted GPMs · SKA Assessor (Welscape) Site visits plus a mid-construction status report flagging measures at risk.S5 ISSUED |
All targeted GPMs | SKA Assessor | |||||||
| HANDOVER STAGE assessment reportHANDOVER STAGE assessment report All targeted GPMs · SKA Assessor (Welscape) Evidence pack compiled, actuals verified, final rating issued.S6 ISSUED |
All targeted GPMs | SKA Assessor | |||||||
| Waste & resource management | |||||||||
| ALLPre-refurbishment auditPre-refurbishment audit D72 · Main contractor / PCSA · scoped in for all fit-outs The manual is explicit: undertaken during Concept Design, equivalent to RIBA Stage 2. Must be issued to the team by end of Stage 2 — it sets every downstream waste decision.S1 active · S2 ISSUED |
D72 | Main contractor | |||||||
| ALLDesigning out waste workshopsDesigning out waste workshops D60 · Design team / specifier · scoped in for all fit-outs Design-stage workshops, then a second round with the contractor and subcontractors at onboarding. Outputs feed the RMP.S2 workshop · S3 ongoing · S4 workshop · S5 workshop |
D60 | Design team | |||||||
| ALLResource Management Plan (RMP)Resource Management Plan (RMP) D09 · Main contractor / PCSA · scoped in for all fit-outs Opened once the pre-refurbishment audit lands, reviewed at design stage, updated on site, closed at handover.S1 active · S2 active · S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D09 | Main contractor | |||||||
| Waste targets — fit-out fabric & servicesWaste targets — fit-out fabric & services D12 · D14 · D13 · D74 · D48 · D68 · Main contractor / PCSA Reduction targets for gypsum, floor finishes, ceilings, raised access floor, doors and M&E services. Recorded in the RMP.S2 active · S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D12 · D14 · D13 · D74 · D48 · D68 | Main contractor | |||||||
| Waste targets — furniture & equipmentWaste targets — furniture & equipment D16 · D15 · D17 · D18 · D61 · D75 · Main contractor / PCSA Reduction targets for chairs, workstations, storage, loose furniture, shopfitting display and specialist workbenches.S2 active · S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D16 · D15 · D17 · D18 · D61 · D75 | Main contractor | |||||||
| Furniture & consumables inventoriesFurniture & consumables inventories P15 · P16 · Main contractor / PCSA Signed-off inventories of what is being stripped out, with re-use routes. Must precede strip-out.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
P15 · P16 | Main contractor | |||||||
| Packaging waste reductionPackaging waste reduction D73 · Main contractor / PCSA Reusable packaging requirement written into specifications and supplier contracts from Stage 2.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D73 | Main contractor | |||||||
| Energy & carbon | |||||||||
| Energy modellingEnergy modelling D66 · MEP, energy, acoustic & air quality consultants Operational energy forecast for the fitted-out space; design model at Stage 4, as-built check at Stage 6.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D66 | Technical consultants | |||||||
| Passive design approachPassive design approach E29 · MEP, energy, acoustic & air quality consultants Orientation, fabric, shading and natural ventilation. Locks at spatial coordination — cannot be added later.S1 active · S2 active · S3 ISSUED · S4 ongoing |
E29 | Technical consultants | |||||||
| Lighting design, efficacy & controlsLighting design, efficacy & controls D01 · E04 · E02 · D02 · E01 · MEP, energy, acoustic & air quality consultants Installed power density, LED efficacy, control zoning and controllability.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D01 · E04 · E02 · D02 · E01 | Technical consultants | |||||||
| Daylighting & secondary glazingDaylighting & secondary glazing D04 · E28 · MEP, energy, acoustic & air quality consultants Daylight improvement and secondary window treatments. Fabric-dependent, so fixed at spatial coordination.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
D04 · E28 | Technical consultants | |||||||
| HVAC efficiency, heat pumps & zone controlsHVAC efficiency, heat pumps & zone controls E05 · E06 · D03 · MEP, energy, acoustic & air quality consultants Plant selection, zoning and control strategy for heating, cooling and ventilation.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E05 · E06 · D03 | Technical consultants | |||||||
| Hot water & primary energy sourceHot water & primary energy source D05 · E11 · MEP, energy, acoustic & air quality consultants DHW efficiency and the primary energy source serving the demise.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D05 · E11 | Technical consultants | |||||||
| Ancillary & specialist equipment efficiencyAncillary & specialist equipment efficiency E22 · D52 · E26 · E24 · D54 · MEP, energy, acoustic & air quality consultants IT comms rooms, entrances, commercial service cabinets, hand-dryers and lifts.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E22 · D52 · E26 · E24 · D54 | Technical consultants | |||||||
| Energy sub-metering strategyEnergy sub-metering strategy E09 · E08 · E25 · MEP, energy, acoustic & air quality consultants End-use, thermal and specialist-area sub-metering. Layout must be fixed before first fix.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E09 · E08 · E25 | Technical consultants | |||||||
| Water & building services pollution | |||||||||
| Sanitaryware & water efficiencySanitaryware & water efficiency E14 · E23 · E12 · E16 · MEP, energy, acoustic & air quality consultants Tap flow rates, WC flush volumes and shower efficiency.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E14 · E23 · E12 · E16 | Technical consultants | |||||||
| Water shut-off, leak detection & meteringWater shut-off, leak detection & metering E19 · E20 · E17 · E27 · E18 · MEP, energy, acoustic & air quality consultants Sanitary supply shut-off, leakage detection, meters, sub-meters and management software.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E19 · E20 · E17 · E27 · E18 | Technical consultants | |||||||
| Refrigerants — GWP, leak control & recoveryRefrigerants — GWP, leak control & recovery D23 · D57 · D24 · D27 · MEP, energy, acoustic & air quality consultants Technical design items — refrigerant selection, leak prevention, detection and recovery land at Stage 4, not concept.S4 ISSUED · S5 ongoing · S6 ISSUED |
D23 · D57 · D24 · D27 | Technical consultants | |||||||
| Plant noise limitsPlant noise limits D25 · MEP, energy, acoustic & air quality consultants Acoustic strategy for external plant against background noise targets; verified on site.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D25 | Technical consultants | |||||||
| Materials & product specification | |||||||||
| Materials specification strategyMaterials specification strategy D19 · Design team / specifier The overarching commitment that SKA materials criteria are written into the specification. Issued at Stage 3 so it binds the tender package.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing |
D19 | Design team | |||||||
| Timber & hardwoods chain of custodyTimber & hardwoods chain of custody D20 · M05 · Design team / specifier Considered from Stage 2 to protect chain of custody through procurement; the full CoC pack is only issuable at end of construction once every subcontractor's documentation is in.S2 active · S3 ongoing · S4 active · S5 ISSUED |
D20 · M05 | Design team | |||||||
| Responsible sourcing, recycled content & EPDResponsible sourcing, recycled content & EPD D81 · D21 · D83 · Design team / specifier Percentage targets across the whole material schedule — they can only be verified once the schedule is complete.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D81 · D21 · D83 | Design team | |||||||
| Spec — partitions, ceilings & floorsSpec — partitions, ceilings & floors M08 · M09 · M10 · M12 · M11 · M07 · M03 · Design team / specifier Partitions, glazed partitions, ceilings, soft and hard flooring, raised floors and screed.S2 active · S3 active · S4 ISSUED · S5 ongoing |
M08 · M09 · M10 · M12 · M11 · M07 · M03 | Design team | |||||||
| Spec — walls, doors, joinery & finishesSpec — walls, doors, joinery & finishes M16 · M13 · M17 · M06 · M27 · M14 · M15 · D63 · M04 · M02 · Design team / specifier Wall coverings, doors, joinery, countertops, paints, polishes, insulation and bricks.S2 active · S3 active · S4 ISSUED · S5 ongoing |
M16 · M13 · M17 · M06 · M27 · M14 · M15 · D63 · M04 · M02 | Design team | |||||||
| Spec — furniture & seatingSpec — furniture & seating M20 · M29 · M19 · M21 · M22 · Design team / specifier Task seating, soft seating, workstations, storage and other loose furniture.S2 active · S3 active · S4 ISSUED · S5 ongoing |
M20 · M29 · M19 · M21 · M22 | Design team | |||||||
| Spec — washroom, signage & ancillarySpec — washroom, signage & ancillary M28 · M24 · M18 · M23 · M25 · M26 · Design team / specifier WC cubicles and IPS, dispensers, kitchen fittings, window treatments, display equipment and signage.S2 active · S3 active · S4 ISSUED · S5 ongoing |
M28 · M24 · M18 · M23 · M25 · M26 | Design team | |||||||
| Low-GWP insulationLow-GWP insulation D22 · Design team / specifier Blowing-agent GWP limits — a specification decision that has to precede the insulation package.S2 active · S3 active · S4 ISSUED · S5 ongoing |
D22 | Design team | |||||||
| Product evidence pack (EPD / Ecolabel / CoC)Product evidence pack (EPD / Ecolabel / CoC) All M-series · D20 · D83 · Design team / specifier Certification checked from Stage 2 as products are shortlisted. Design stage pack at Stage 4; as-installed pack, covering substitutions, at handover.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
All M-series · D20 · D83 | Design team | |||||||
| Wellbeing & indoor environment | |||||||||
| Thermal comfort assessmentThermal comfort assessment D28 · MEP, energy, acoustic & air quality consultants Modelled comfort criteria for the fitted-out space; verified post-commissioning.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D28 | Technical consultants | |||||||
| Acoustic designAcoustic design D29 · MEP, energy, acoustic & air quality consultants Room acoustics and sound insulation across teaching, study and lab spaces.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D29 | Technical consultants | |||||||
| Lighting design & glare controlLighting design & glare control D30 · D31 · MEP, energy, acoustic & air quality consultants Illuminance, quality and daylight glare control — distinct from the D01 energy criteria.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D30 · D31 | Technical consultants | |||||||
| Ventilation rates, occupant control & CO₂Ventilation rates, occupant control & CO₂ D33 · D32 · D40 · MEP, energy, acoustic & air quality consultants Fresh air rates, local HVAC controllability and CO₂ monitoring.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D33 · D32 · D40 | Technical consultants | |||||||
| Air quality — filtration & ductworkAir quality — filtration & ductwork D37 · D36 · D64 · MEP, energy, acoustic & air quality consultants Fine filters, cleaning of existing supply ductwork, low-VOC finishes and VOC monitors.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D37 · D36 · D64 | Technical consultants | |||||||
| Outside views & biophilic designOutside views & biophilic design D39 · D77 · Design team / specifier View lines and biophilic strategy — both depend on the plan, so they fix at spatial coordination.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
D39 · D77 | Design team | |||||||
| Breakout space & personal storageBreakout space & personal storage D62 · D76 · Design team / specifier Dedicated breakout provision and personal storage allocation on the floor plate.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
D62 · D76 | Design team | |||||||
| Laboratory & specialist spaces | |||||||||
| Good laboratory design reviewGood laboratory design review D82 · Design team / specifier HE-specific. Lab layout, containment, servicing and flexibility reviewed against the criteria.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D82 | Design team | |||||||
| Fume cupboards & specialist ventilationFume cupboards & specialist ventilation E30 · D51 · D35 · MEP, energy, acoustic & air quality consultants Fume cupboard selection and operation, specialist ventilation, and printer-copier area extract.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
E30 · D51 · D35 | Technical consultants | |||||||
| Air quality impact assessment (flues)Air quality impact assessment (flues) P17 · MEP, energy, acoustic & air quality consultants Dispersion analysis on new fume cupboard, safety cabinet or boiler flues. Feeds back into flue design, so it must run before the design freezes.S2 active · S3 ongoing · S4 ISSUED |
P17 | Technical consultants | |||||||
| Laboratory furniture storage logisticsLaboratory furniture storage logistics P13 · Main contractor / PCSA Framework for maximising re-use of lab furniture over recycling, with a signed-off removal inventory.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
P13 | Main contractor | |||||||
| Space planning, transport & ecology | |||||||||
| Cycle parking, showers & cyclist lockersCycle parking, showers & cyclist lockers D41 · D42 · D43 · Design team / specifier Floor and core area reserved at concept and fixed at spatial coordination — cannot be retro-fitted.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
D41 · D42 · D43 | Design team | |||||||
| Travel plans — building & campusTravel plans — building & campus D78 · D79 · University estates, client & PM University-level documents. Often already exist — confirm currency early rather than commissioning late.S1 active · S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
D78 · D79 | Client / university | |||||||
| ALLRecyclable waste storage spaceRecyclable waste storage space D08 · Design team / specifier · scoped in for all fit-outs Segregated storage sized and located on the floor plate; layout fixed at Stage 3.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
D08 | Design team | |||||||
| BiodiversityBiodiversity D80 · Design team / specifier Space for biodiversity designed in — roof, terrace or external area. Needs to land while the design still has room for it.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ISSUED |
D80 | Design team | |||||||
| Soft Landings, handover & training | |||||||||
| ALLSoft Landings design workshopsSoft Landings design workshops D69 · Design team / specifier · scoped in for all fit-outs The manual states the Soft Landings process starts at RIBA Stage 2 and continues for three years after practical completion.S1 active · S2 workshop · S3 workshop · S4 workshop |
D69 | Design team | |||||||
| ALLSoft Landings commissioning & trainingSoft Landings commissioning & training D70 · Main contractor / PCSA · scoped in for all fit-outs Commissioning records, operator training and handover programme.S4 active · S5 ongoing · S6 ISSUED |
D70 | Main contractor | |||||||
| ALLBuilding User GuideBuilding User Guide D45 · Main contractor / PCSA · scoped in for all fit-outs Plain-language occupant and estates guide. Committed at design stage, issued at handover.S4 active · S5 ongoing · S6 ISSUED |
D45 | Main contractor | |||||||
| Construction-phase monitoring | |||||||||
| ALLFit-out energy useFit-out energy use P01 · Main contractor / PCSA · scoped in for all fit-outs Commitment at design stage, metered through the works, records reviewed at handover.S4 active · S5 ongoing · S6 ISSUED |
P01 | Main contractor | |||||||
| ALLFit-out water useFit-out water use P07 · Main contractor / PCSA · scoped in for all fit-outs Metered through the works; data uploaded to the SKA tool at project end.S4 active · S5 ongoing · S6 ISSUED |
P07 | Main contractor | |||||||
| ALLFit-out VOC monitoringFit-out VOC monitoring P12 · Main contractor / PCSA · scoped in for all fit-outs VOC levels monitored and recorded on site through the fit-out.S4 active · S5 ongoing · S6 ISSUED |
P12 | Main contractor | |||||||
| Construction phase CO₂ emissionsConstruction phase CO₂ emissions D59 · Main contractor / PCSA Deliveries, waste removal and site energy logged through construction.S4 active · S5 ongoing · S6 ISSUED |
D59 | Main contractor | |||||||
Hover any row for what it requires and when.
Stage 2 is the pinch point, and here the manual says so outright: the pre-refurbishment audit is to be undertaken “during Concept Design stage, equivalent to RIBA stage 2”, and Soft Landings “starts at RIBA stage 2”.
Stage 4 freezes the design for most measures — but not all. D72, D60, D19 and the space-planning measures are constrained earlier; D20 chain of custody cannot be closed until every subcontractor's documentation is in at end of construction.
Version 1 carries almost no RIBA staging of its own. Only D72 and the three Soft Landings measures name a RIBA stage. The stage placings here are reasoned from what each measure requires, not quoted from the manual.
Six GPMs sit outside RIBA 0–6. P05, P06, P08, P10 and P11 each state they can only be assessed after a minimum of one year's occupation; D71 Soft Landings aftercare runs three years past practical completion.