SKA Offices 2.0, stage by stage
What's due when, and what it costs to miss it
This is how I run a SKA Offices Environmental 2.0 assessment, laid out against the RIBA stages. For each piece of work it says what has to happen, by when, who usually does it and roughly what kind of cost it is.
It's built from SKA's Good Practice Measures 2.0. Where a measure sets its own deadline, the roadmap says so. Where it doesn't, I've put the work where it needs to happen for the evidence to exist, and marked it as mine.
- 83measures in Offices 2.0, across nine categories
- 16apply to every fit-out, whatever its scope
- 3are only assessed at the optional occupancy stage
How the score works
SKA rates a project on the share of its in-scope measures that are achieved: 25% and above for Bronze, 50% for Silver and 75% for Gold. So the count matters as much as the measures.
SKA also ranks every measure by impact. Earlier versions of the scheme made each rating include some of the top-ranked measures, known as gateway measures, so I confirm any gateway requirements for your project at scoping.
Scope sets the count
Measures come into scope by what the works include, and SKA audits assessors on scoping. You can't drop one that applies. The only choices are the opt-ins: D47, D87, D90 and E29, plus D89 at £500k or less and D08 on a Cat A fit-out. One oddity: D84 applies to every fit-out, but D09's criteria call it optional at £2m or less, so I confirm how it's treated on each project.
Sixteen are always in
They apply to every fit-out, so they're in your count whether you plan for them or not. Most are workshops, plans and records. Add D89, the embodied carbon LCA, unless the build cost is £500k or below.
Some can't be recovered
The pre-refurbishment audit has to be done during Concept Design and isn't re-assessed at handover. D86 happens before the lease is agreed. D07 has to be in the tender before contractors are picked. Lighting sub-metering decides P10 at occupancy. And D09 needs D72, D60 and D07, so losing any of them loses D09 as well.
The count at each threshold
| In scope | Bronze | Silver | Gold |
|---|---|---|---|
| 40 | 10 | 20 | 30 |
| 50 | 13 | 25 | 38 |
| 60 | 15 | 30 | 45 |
| 70 | 18 | 35 | 53 |
Rounded up. SKA rates a project on the share of in-scope measures achieved: 25% and above for Bronze, 50% for Silver and 75% for Gold.
Opting in cuts both ways. At 30 of 40 measures you're on 75%, the Gold line. Opt into D90, miss the limit, and 30 of 41 is 73%.
The sixteen every fit-out carries
Plan these from day one. They're cheap to win and they cost you points whether you try or not. Each tile shows when it's due, or when I'd do it.
D86
Landlord and tenant collaboration
Before the agreement for lease
D88
Project delivery programme
Set up during Stage 1
D09
Resource Management Plan and Tracker
Stage 1 or 2 to handover, and needs D72, D60 and D07
D72
Pre-refurbishment audit
During Concept Design
D60
Design for whole life resource optimisation
Workshops at concept and subcontractor onboarding
D69
Soft Landings design workshops
Design team and contractor workshops, targets checked in use
D44
Project sustainability delivery plan
In the tender, then on site
D07
Site Waste Management Plan
In the tender, written before site starts
D73
Packaging
Suppliers lined up in the tender
D84
Fixed asset tagging and register
Tags in the scope, register at handover
D59
Construction transport CO₂
Travel plan at design, tracked on site
P01
Fit-out energy use
Readings at least fortnightly
P07
Fit-out water use
Readings at least fortnightly
D70
Soft Landings commissioning, handover and training
Commissioning manager during design
D71
Soft Landings aftercare
Contract at design, aftercare schedule at handover
D45
Building User Guide
Writer contracted at design, guide at handover
The roadmap, stage by stage
Every measure in Offices 2.0 sits somewhere on this list. Each item says what to do, when, who usually does it and what kind of cost it is.
Deadline set by the measure itself
When I would do it
-
RIBA Stage 0: Strategic Definition
Before there's a brief. Only one measure can be lost this early, and it's an easy one to lose.
-
Suggested timing: At the start
Pick the scheme, the target and the boundary
Confirm Offices 2.0 fits the space, agree the rating you're after and fix what's inside the project boundary. SKA's online tool is free, so the project can be registered and scoped before anyone's appointed.
-
Deadline set by the scheme: Before the agreement for lease is finalised
Landlord and tenant energy workshop
D86
A workshop with the landlord on cutting energy and carbon across both demises for the length of the tenancy, end-of-lease dilapidations included. The actions go into the landlord's or tenant's works and into the agreement for lease.
If it slips: The GPM ties the workshop to the lease negotiations and offers no other route. If the lease is already signed, raise it at the start.
-
-
RIBA Stage 1: Preparation and Briefing
Set up the two documents everything else hangs off, and decide which optional measures you're going for.
-
Deadline set by the scheme: During Stage 1
SKA project delivery programme
D88
One programme from brief to post-completion. It has to show when the surveys and resource workshops happen, time to procure reused products, disassembly and storage during the works, and the post-occupancy reviews.
If it slips: The criteria say it's set up during Stage 1, so it can't wait for the contractor's programme.
-
Deadline set by the scheme: Set up in Stage 1 or 2
Resource Management Plan and Tracker (RMPT)
D09
The schedule that follows every existing and new material from the audit to where it ends up, with estimated and actual quantities and a named owner for each action. It's reviewed at the design stage and again at handover.
If it slips: D09 can only be achieved if D72, D60 and D07 are achieved, and D84 too on projects over £2m. Lose one of those and D09 goes with it.
-
Suggested timing: Before Concept Design
Decide the opt-in measures
D90D47D87E29
Four measures only count if you choose them: Embodied Carbon Intensity, whole life carbon, the LCA comparison and the energy demand study. D89 is optional too at £500k or less, and so is D08 on a Cat A fit-out. Each one you take on adds a measure to the in-scope count, so only take on the ones you'll achieve. D90 with D85 is what unlocks SKA's Net Zero aligned certificate.
-
Suggested timing: Before Concept Design
Book the carbon and energy specialists
D89D66
On projects of £4m and over, D89 needs a predictive LCA at Stage 2, so the LCA consultant has to be on board before Concept Design. D66 needs a CIBSE TM54 energy forecast: dynamic simulation over £2m, steady state allowed below.
-
-
RIBA Stage 2: Concept Design
The pinch point. The audit, the first resource workshop, the Soft Landings targets and the first LCA all happen here, and the audit can't be done later.
-
Deadline set by the scheme: During Concept Design
Pre-refurbishment audit
D72
An experienced designer or other competent person surveys what's there: ceilings, wall and floor finishes, raised floors, partitions, doors, joinery and kitchens, furniture (including what the client already owns), light fittings and controls, and M&E. It records quantities, estimates the waste if it were all thrown away, and identifies what can be kept or reused.
If it slips: It isn't re-assessed at handover, so once Concept Design has passed it's lost, and D09 goes with it. The other resource management measures are checked against what the audit lists, so they get harder.
-
Deadline set by the scheme: One workshop during Concept Design
First resource optimisation workshop
D60
Work through SKA's design principles with the design team and direct suppliers, from avoiding unnecessary work to designing for repair and disassembly and reusing what's already there. Every decision goes into the RMPT.
If it slips: D60 needs two workshops, this one and another at subcontractor onboarding. Skip either and D60 fails, and so does D09.
-
Suggested timing: From Stage 2
Soft Landings design workshop
D69
The design team, the contractor if appointed, an end-user representative and whoever will run the space. Review lessons from past projects, set roles and set specific, measurable performance targets, such as in-use energy. D69 also needs a design intent workshop with the contractor once they're on board.
If it slips: Both workshops are required. Handover checks the systems can hit the targets and occupancy checks they did, so vague targets come back to bite.
-
Deadline set by the scheme: Stage 2 report
Embodied carbon LCA, first report
D89D90D47
A predictive upfront carbon LCA of the whole scope of works, direct purchases included, to the RICS whole life carbon methodology. On £4m and over it's Stages 2 and 4 plus an as-built report at Stage 6. Under £4m you can do Stages 2 and 4, or Stage 6 only. With D90, the Stage 2 and 4 results have to meet the UK Net Zero Carbon Buildings Standard upfront limit for the year you start on site. D47 runs the same stages over the whole life cycle.
If it slips: On £4m and over a missed Stage 2 report can't be made up later.
-
Suggested timing: While the options are open
Energy and carbon options studies, if chosen
E29D87
E29 is an options study on cutting operational energy: daylight, heating and cooling demand, natural or mixed-mode ventilation and plant efficiency. D87 compares the whole life carbon of at least four of five elements: keeping or replacing light fittings, partition types, suspended ceiling against open soffit with baffles, pods against cellular rooms, and one more of your choice.
-
-
RIBA Stage 3: Spatial Coordination
The plan gets fixed. Anything that needs floor area or a meter has to be on the drawings now.
-
Suggested timing: Fix on the plan
Cycle parking, showers, lockers and the recycling store
D41D42D43D08
One cycle space per 100 m² of net internal area, or per 10 people if the occupancy is known. One shower per 100 non-transient occupants. One keyless locker per 8 staff. A recycling store sized from an operational waste strategy for the occupier.
If it slips: These take floor area, and adding them once the layout's coordinated means moving things.
-
Suggested timing: Design to it
Lighting design
D01D02E04
300 to 500 lux in continuously occupied areas and 100 lux front and back of house, inside SKA's LENI energy limits. Automatic presence and daylight control, separate perimeter and central zones, and zones that follow the layout. Every fitting on the Energy Technology List or meeting its criteria.
-
Suggested timing: Design it in
Energy and water metering
E08E17P10
Energy sub-metered by end use, lighting and small power included, on a system that meets the Energy Technology List criteria. A pulse water meter on the tenant's supply and sub-meters on big users such as a kitchen or gym changing, all reporting to a data logger or BMS.
If it slips: If D01, D02 or E04 are in scope, P10 comes into scope at the occupancy stage. Without lighting sub-metering it stays in scope but can't be achieved.
-
Suggested timing: If new plant makes external noise
Plant noise
D25
A BS 4142 noise impact assessment, yours or one the landlord already holds, or a report showing new plant stays within 5 dB of background or setting out the attenuation that gets it there. Either way the installed plant has to match the report and a qualified acoustic consultant has to confirm it.
-
Suggested timing: Design to it
Healthy internal conditions
D28
Ventilation rates and comfort conditions to the CIBSE Guide A minimums and lux levels to the CIBSE Code for Lighting, wherever ventilation, heating, cooling or lighting are changed.
-
-
RIBA Stage 4: Technical Design
Most measures are won or lost in the specification and the tender documents. My design stage assessment comes at the end of this stage.
-
Suggested timing: In every specification
Specify every product to its criteria
M03M04M06M07M08M10M11M12M13M14M16M17M18M19M20M21M22M23M29M30M31M32M33D20
Most materials measures work the same way: each product is reused, or comes from a manufacturer's closed-loop take-back scheme with a Product Circularity Data Sheet, or is new and meets one of the listed routes, such as an upfront carbon limit, an EPD or a recognised certification. Most also need a disassembly guide with every product, and light fittings need a demountability guide. Watch the exceptions: light fittings (M32) and cables, pipes, ducts and controls (M31) need a reused or take-back share as well as compliant new products, and screed and paints have no reuse route. All timber, furniture included, must be reclaimed or come with certified chain of custody to site. Furniture the client buys direct is in scope too.
If it slips: Specifications are checked at design stage and delivery notes at handover, so a substitution on site can lose a measure you'd already banked.
-
Suggested timing: In the M&E specification
Plant, refrigerants and leaks
E05E31M30D23D57
Heat pumps and heat recovery units on the Energy Technology List or meeting its criteria. Refrigerant systems at no more than 1,000 kgCO₂e per kW of cooling capacity, shown by a DELC calculation to BS EN 378-1 from the manufacturer or installer. Leak prevention to BS EN 378-1 and REAL Zero guidance written into the specification.
-
Suggested timing: In the specification
Water fittings
E14E19E20
Taps, cleaners' sinks aside, at 4 litres a minute or less up to 5 bar, with a Unified Water Label, and auto shut-off within 20 seconds where it's fitted. A shut-off on the washroom cold supply when nobody's in, and a leak detection system with an adjustable alarm.
-
Suggested timing: By the design stage assessment
Energy model and Energy Use Intensity
D66D85
A CIBSE TM54 forecast of the fitted-out space in kWh/m² a year, using base build data where you can get it. D85 compares it with the UK Net Zero Carbon Buildings Standard limit for the year the fit-out starts on site, from the Annex A table that matches the base build.
If it slips: D85 can't be achieved without the D66 model, and both are checked again at handover against the as-built drawings.
-
Deadline set by the scheme: Stage 4 report
Embodied carbon LCA, second report
D89D90D47
The predictive LCA updated for the technical design. With D90, this is the report that shows whether you're inside the limit before anything's bought.
-
Deadline set by the scheme: Before contractors are selected
Waste plan requirements in the tender
D07
The project requirements sent to tenderers include all of D07's criteria: a Site Waste Management Plan targeting 95% diversion from landfill of unavoidable non-hazardous waste, and a licensed waste contractor certified to PAS 402 or providing the same data.
If it slips: D07 is checked against what went to contractors before they were picked. Add it after award and it's lost, and D09 with it.
-
Suggested timing: In the tender
The rest of SKA in the tender
D44D73P01P07P19D84D60D59
D44, D73, P01 and P07 are checked against the procurement information, so the tender asks for a construction environmental and sustainability plan; returnable packaging from at least four of plasterboard and dry lining, timber sheet, glass, paint, joinery, furniture and light fittings; and energy and water metered on site at least fortnightly, with at least five readings. Water pollution controls, an ID tag on every item installed or adapted, and subcontractors at a resource workshop are easiest to secure there too. A design-stage travel plan estimates the transport emissions of deliveries and waste.
-
Deadline set by the scheme: During design
Commissioning manager, aftercare and the user guide
D70D71D45
The contractor's commissioning manager appointed during the design stage. A contract or client commitment for the designer and contractor to come back and fine-tune through the first year, with a named point of contact. And a named organisation contracted to write the Building User Guide.
If it slips: If the contractor won't be appointed until after Stage 4, talk to me early about how D70 can still be met.
-
Suggested timing: Record in the RMPT
Reuse decisions for everything that's coming out
D06D12D13D14D15D16D17D18D34D38D46D48D68D74
For each existing item in the audit, record where it's going: reused here or on another project, back to the manufacturer for closed-loop recycling, or diverted from landfill. Most have their own minimum, for example 40% of removed partitions and ceilings and 50% of removed light fittings reused or taken back. Reused items need a Product Circularity Data Sheet.
-
Suggested timing: End of Stage 4
Design stage assessment
I check the drawings, specifications, calculations and commitments against every targeted measure and report what's achieved, what's at risk and what's needed from whom.
-
-
RIBA Stage 5: Manufacturing and Construction
Evidence gets made or lost on site. Most of it is paperwork that's easy to collect at the time and painful to rebuild later.
-
Suggested timing: On contractor appointment
Design intent workshop with the contractor
D69
The second D69 workshop: take the contractor through the design intent and the Soft Landings performance targets.
If it slips: Skip it and D69 fails, however good the design workshop was.
-
Deadline set by the scheme: During subcontractor onboarding
Second resource optimisation workshop
D60
Take the subcontractors through the same design principles and update the RMPT with what they commit to.
If it slips: Without it D60 isn't achieved, however good the first workshop was.
-
Deadline set by the scheme: Before site works start
Site Waste Management Plan
D07
The contractor's SWMP, tied to the unavoidable waste streams in the RMPT, with the 95% diversion target, projected quantities and a licensed waste contractor certified to PAS 402 or providing the same data.
-
Deadline set by the scheme: At least every three months
Keep the RMPT live
D09
Handed to a named manager in the construction team and updated at least once in every three-month period, with the SWMP's waste streams and quantities.
-
Deadline set by the scheme: At least fortnightly
Meter readings and site records
P01P07D59P19
Energy and water meter readings at least once a fortnight, at least five over the job. Delivery and waste vehicle movements tracked against the travel plan. Wash water from paints, plaster, screed, grout and adhesives filtered and pH-treated, commissioning water treated, and records kept.
-
Suggested timing: As products arrive
Delivery notes and chain of custody
D20
Every delivery note or invoice for new or recycled timber needs the supplier's name and dispatch depot, quantities, the product, the claim (70% Mix at least) and the chain of custody certificate number. Furniture can show chain of custody to the supplier's consolidation store plus its delivery note to site. Keep delivery notes for every specified product, and check substitutions against the specification before they're ordered.
-
Suggested timing: Throughout
Packaging back, tags on
D73D84
Returnable packaging goes back to the suppliers. All single-use plastic packaging is recorded in the RMPT and SWMP and segregated for recycling. Asset tags go onto every item installed or adapted.
-
Deadline set by the scheme: Before handover
Commissioning and training
D70
Operators trained through their involvement in commissioning and testing, and a short commissioning report written for them.
-
Suggested timing: Usually twice
My site visits
I normally visit twice and send a mid-construction report on measures at risk, while there's still time to fix them.
-
-
RIBA Stage 6: Handover
Certification starts here, once the evidence pack is complete.
-
Deadline set by the scheme: Stage 6 report
As-built LCA
D89D90D47
The LCA as delivered, for projects of £4m and over or on the Stage 6 route, submitted to the Built Environment Carbon Database. SKA's handover check asks for evidence of upload for each stage, so upload the Stage 2 and 4 data too. D90 is checked against the Stage 6 actuals report, so plan for one if you've opted in, whichever route D89 took.
-
Deadline set by the scheme: At completion
Final waste and resource records
D07D09D84
The final SWMP and the waste contractor's report, showing 95% of unavoidable non-hazardous waste diverted from landfill. The final RMPT with actual quantities and destinations. The asset register, set up or updated for the occupier's facilities team, linking each tag to the material, manufacturer, warranty, installation date and location, the EPD or PCDS, data sheet, deconstruction guide and end-of-life requirements.
-
Deadline set by the scheme: At handover
User guide, training records and handover information
D45D70
Building User Guides for the facilities manager and the occupants, in plain language. Signed training records, the commissioning summary, and handover information in the format agreed in the handover plan.
-
Deadline set by the scheme: At handover
Aftercare in place
D71
A Soft Landings responsibilities schedule naming the point of contact, with time on site for walkabouts through the first 8 weeks of occupation: at least a day a week, or a day a fortnight under £2m. And the contractor appointed to validate sub-meter readings after 2 or 3 months of operation.
If it slips: The occupancy stage is optional, so on most projects this is the evidence that decides D71.
-
Deadline set by the scheme: At completion
Fit-out energy and water totals
P01P07
Total energy in kWh and total water for the works, sent to me to pass on to SKA.
-
Deadline set by the scheme: At the handover stage
Lighting and small power meter readings
P10P11
Read and record the lighting and small power sub-meters. The occupancy stage works out a year's use from the difference between these readings and later ones.
If it slips: P10 is worked out from the handover readings, so missing them puts it at risk. P11 can use any full year within the first two years of occupation.
-
Deadline set by the scheme: At handover
As-built energy check
D66D85
As-built Energy Use Intensity calculations, with the as-built drawings and equipment schedules checked against the energy model's inputs.
-
Suggested timing: Certification
Handover assessment and certificate
I compile the evidence pack, check actuals against the targets and issue the certificate. SKA says certification takes from a couple of days to a few weeks once the assessment's done, depending on the payment method and how many previews and changes are asked for.
-
-
RIBA Stage 7: Use: the optional occupancy stage
Between 12 and 24 months after handover. Mostly a check on what's changed, plus three measures that only exist here.
-
Deadline set by the scheme: A full year of data
Lighting and small power in use
P10P11
A year of metered lighting energy per m², and small power against the CIBSE Guide F benchmarks for the type of space. P11 is in scope on every occupancy assessment.
-
Deadline set by the scheme: If the tenant can buy its own energy
Renewable energy contracts
P18
Electricity backed by REGO certificates or a power purchase agreement with a 100% renewable generator, and gas with RGGO or Biomethane Certificate Scheme backing, with the certificates in the tenant's name.
-
Deadline set by the scheme: 12 months after completion
Aftercare and post-occupancy evaluation
D71D69
Fine-tuning through the first year and a post-occupancy evaluation 12 months after completion and full occupation, against the Soft Landings targets. D69 is checked on whether those targets were met in year one.
-
Deadline set by the scheme: At the occupancy assessment
Everything else
Most measures achieved at handover are achieved by default if nothing's changed, and anything changed or added is assessed again. Some are checked anyway: D85 against measured energy use, D57 against the refrigerant maintenance records, D08 with a site visit, D45 that the user guides are still available, and E29 that its measures are still in place.
-
Where the money goes
My rough guide from projects, not SKA's, and every fit-out is different. The point is that most of the score is effort and timing rather than spend.
Team time
Most of the sixteen: the programme, the workshops, the plans, the records and the user guide. They cost meetings and paperwork, and each one counts towards the share like any other measure.
Specialist fees
The LCA at Stages 2, 4 and 6, and D90 or D47 on top if you opt in. The TM54 energy model. A noise assessment if there's new plant. Lighting energy calculations. Book them at Stage 1 so the Stage 2 work happens on time.
Products, kit and space
ETL-listed plant and lighting, products with EPDs, take-back schemes or certification, sub-meters, leak detection and washroom shut-off, and floor area for cycling and recycling. Specified early, most of these are choices rather than extras.
The expensive mistakes
- Skipping the Stage 2 audit. D72 is gone, D09 goes with it, and the other resource management measures that lean on the audit get harder.
- Leaving SKA out of the tender. D07 has to be in front of contractors before they're picked, and adding the rest after award means variations.
- No lighting sub-meter. P10 comes into scope at occupancy and can't be achieved.
- Opting in and missing. An opt-in you don't achieve lowers your percentage.
- Substitutions on site. A cheaper product that doesn't meet the criteria loses a measure you'd already won at design stage.
All 83 measures
What brings each measure into scope, and the stage where the work on it starts. Open a category to see its measures.
Energy
13 measures
D01Energy efficient lighting
In scope when: A general lighting system serving an area over 20 m² is installed or upgraded
Work starts: Stage 3
D02Lighting controllability
In scope when: New lighting, or existing controls replaced
Work starts: Stage 3
D66Energy modelling
In scope when: Changes to energy-consuming systems
Work starts: Stage 1
D85Energy Use Intensity
In scope when: Any change to energy-consuming systems
Work starts: Stage 4
D86Landlord and tenant collaboration
In scope when: Always
Work starts: Stage 0
E04Energy efficient light fittings
In scope when: New internal or external light fittings, integrated lamp and fitting only
Work starts: Stage 3
E05Energy efficient heat pumps
In scope when: New heat pumps of the listed types
Work starts: Stage 4
E08Energy measurement and reporting
In scope when: Energy-consuming systems installed or modified, unless compliant metering already exists; landlord-controlled central HVAC excluded
Work starts: Stage 3
E29Energy demand reduction
In scope when: Only if the client chooses to do the study
Work starts: Stage 1
E31Energy efficient ventilation equipment
In scope when: New ventilation supplying outside air, with plate or rotary heat recovery
Work starts: Stage 4
P10Reduce lighting energy in use
In scope when: Occupancy stage only, if D01, D02 or E04 were in scope at handover
Work starts: Stage 3
P11Reduce small power energy in use
In scope when: Occupancy stage only, always
Work starts: Stage 6
P18Zero carbon energy contracts
In scope when: Occupancy stage only, if the tenant buys its own energy
Work starts: Stage 7
Environmental health
1 measure
D28Healthy internal conditions
In scope when: Ventilation, heating, cooling or lighting modified
Work starts: Stage 3
Materials
25 measures
D89Embodied carbon assessment
In scope when: Always, unless the build cost is £500k or below, when it is optional
Work starts: Stage 1
D90Embodied Carbon Intensity
In scope when: Only if the client chooses to claim Net Zero alignment
Work starts: Stage 1
M03Screed
In scope when: Any screed specified or installed
Work starts: Stage 4
M04Insulation
In scope when: Any fire, thermal or acoustic insulation specified or installed
Work starts: Stage 4
M06Joinery
In scope when: Joinery or bespoke specialist doors
Work starts: Stage 4
M07Raised floor systems
In scope when: Raised flooring specified and installed
Work starts: Stage 4
M08Partitions
In scope when: Partitions and wall linings specified, installed or partly modified
Work starts: Stage 4
M10Ceilings
In scope when: Suspended ceilings, panels or membranes specified, installed or partly modified
Work starts: Stage 4
M11Hard floor covering
In scope when: Hard flooring specified or installed
Work starts: Stage 4
M12Soft floor covering
In scope when: Carpet, vinyl, linoleum, rubber and similar, loose rugs included
Work starts: Stage 4
M13Hard wall covering
In scope when: Tiles, panels, acoustic panels, mirrors and similar
Work starts: Stage 4
M14Paints and coatings
In scope when: Any paint or coating, primers included
Work starts: Stage 4
M16Wall covering
In scope when: Wallpaper, films, textile wall coverings or curtains
Work starts: Stage 4
M17Doors
In scope when: Standard doors, with frames and ironmongery
Work starts: Stage 4
M18Kitchen fittings
In scope when: Kitchen fittings in tea points or commercial kitchens
Work starts: Stage 4
M19Desks and tables
In scope when: Loose desks and tables, however they are bought
Work starts: Stage 4
M20Chairs, task seating
In scope when: Task or meeting chairs, however they are bought
Work starts: Stage 4
M21Storage units
In scope when: Loose storage, however it is bought
Work starts: Stage 4
M22Other loose furniture
In scope when: Any other furniture specified, retained, modified, replaced or installed
Work starts: Stage 4
M23Window treatments and curtains
In scope when: Blinds, drapes or curtains
Work starts: Stage 4
M29Chairs, soft seating
In scope when: Soft seating, benches or stools, however they are bought
Work starts: Stage 4
M30HVAC equipment
In scope when: New, relocated or adapted heat pumps, fan coils, air handling or heat recovery units
Work starts: Stage 4
M31Cables, pipes, ducts and lighting controls
In scope when: Any of the listed items new or reused
Work starts: Stage 4
M32Light fittings
In scope when: Architectural and integrated light fittings, new or reused
Work starts: Stage 4
M33Decorative and other light fittings
In scope when: Decorative and other light fittings, new or reused
Work starts: Stage 4
Ecology
1 measure
D20Timber
In scope when: Any timber, furniture and temporary site timber included
Work starts: Stage 4
Pollution
4 measures
D23Low impact refrigerants
In scope when: Any new refrigerant used
Work starts: Stage 4
D25Limiting plant noise
In scope when: New plant that generates external noise
Work starts: Stage 3
D57Refrigerant leak prevention
In scope when: New or changed refrigerant systems, unless under 3 kg charge or GWP under 5
Work starts: Stage 4
P19Construction water pollution
In scope when: Plaster, mortar, concrete, screed, paint, liquid adhesives, tiling and similar in the works, or water used to commission services
Work starts: Stage 4
Project delivery
10 measures
D44Project sustainability delivery plan
In scope when: Always
Work starts: Stage 4
D45Building User Guide
In scope when: Always
Work starts: Stage 4
D47Whole life carbon assessment
In scope when: Only if the client chooses it
Work starts: Stage 1
D69Soft Landings: design workshops
In scope when: Always
Work starts: Stage 2
D70Soft Landings: commissioning, handover and training
In scope when: Always
Work starts: Stage 4
D71Soft Landings: aftercare
In scope when: Always
Work starts: Stage 4
D87LCA impact comparison
In scope when: Only if the client chooses it
Work starts: Stage 1
D88Project delivery programme
In scope when: Always
Work starts: Stage 1
P01Reduce fit-out energy use
In scope when: Always
Work starts: Stage 4
P07Reduce fit-out water use
In scope when: Always
Work starts: Stage 4
Resource management
21 measures
D06Joinery and kitchen fittings
In scope when: Joinery or kitchen fittings modified or removed
Work starts: Stage 4
D07Site Waste Management Plan
In scope when: Always
Work starts: Stage 4
D08Recyclable waste storage space
In scope when: Cat A+ and Cat B fit-outs; optional on Cat A
Work starts: Stage 3
D09Resource Management Plan and Tracker
In scope when: Always
Work starts: Stage 1
D12Partitions
In scope when: Existing partitions or linings removed or adjusted, client direct works included
Work starts: Stage 4
D13Ceilings
In scope when: Existing or new ceilings removed, client direct works included
Work starts: Stage 4
D14Floor coverings
In scope when: Existing or new floor finishes in the contract
Work starts: Stage 4
D15Desks and tables
In scope when: Existing desks and tables removed
Work starts: Stage 4
D16Chairs
In scope when: Existing chairs removed; items containing POPs excluded
Work starts: Stage 4
D17Storage units
In scope when: Existing storage removed
Work starts: Stage 4
D18Other loose furniture
In scope when: Other existing loose furniture removed; items containing POPs excluded
Work starts: Stage 4
D34Wall coverings
In scope when: Existing or new wall coverings in the contract
Work starts: Stage 4
D38Light fittings
In scope when: Existing light fittings relocated or removed
Work starts: Stage 4
D46Cables, pipes, ducts and lighting controls
In scope when: Any of the listed items new, relocated or removed
Work starts: Stage 4
D48Doors
In scope when: Existing doors removed or adjusted
Work starts: Stage 4
D60Design for whole life resource optimisation
In scope when: Always
Work starts: Stage 2
D68HVAC equipment
In scope when: Existing or relocated heat pumps, fan coils, heat recovery or air handling units
Work starts: Stage 4
D72Pre-refurbishment audit
In scope when: Always
Work starts: Stage 2
D73Packaging
In scope when: Always
Work starts: Stage 4
D74Raised floor systems
In scope when: Raised floor panels modified or removed
Work starts: Stage 4
D84Fixed asset tagging and register
In scope when: Always
Work starts: Stage 4
Transport
4 measures
D41Cycle parking
In scope when: Tenant core or external space with suitable access
Work starts: Stage 3
D42Shower facilities
In scope when: Enough washroom space, unless adequate showers are already in the building; always with a commercial kitchen, sports facilities or hot or grimy work
Work starts: Stage 3
D43Cyclist lockers
In scope when: Enough core space, unless enough lockers are already in the building
Work starts: Stage 3
D59Construction phase transport CO₂
In scope when: Always
Work starts: Stage 4
Water
4 measures
E14Efficient taps
In scope when: Taps installed or replaced
Work starts: Stage 4
E17Water measurement and reporting
In scope when: Any work to the water supply, even one tap
Work starts: Stage 3
E19Sanitary supply shut-off
In scope when: Water supply installed or modified
Work starts: Stage 4
E20Water leak detection
In scope when: Water supply installed or modified
Work starts: Stage 4
Scoping wording is shortened from the GPM's. I check every project's scope against the full scheme document.
SKA Offices 2.0 roadmap FAQs
Which measures depend on others?
Several. D09, the resource tracker, can only be achieved if D72, D60 and D07 are achieved, and D84 too on projects over £2m. D85 needs the D66 energy model. D90 needs the D89 LCA, including the Stage 6 actuals report. SKA's Net Zero aligned certificate needs both D85 and D90.
So one missed early deadline can cost two measures, which is why the audit and the first resource workshop matter more than they look.
Can we scope a measure out to protect the score?
Not one that applies. Measures come into scope by what the works include, and SKA audits its assessors on getting the scoping right.
The real choices are the opt-ins: D47, D87, D90 and E29, plus D89 at £500k or less and D08 on a Cat A fit-out. Each one you take on adds a measure to the count, so it only helps if you achieve it.
We're already at Stage 3 or 4. Is it too late?
Not for a certificate, but expect some losses. The D72 audit and the first D60 workshop both belong to Concept Design, and D09 can't be achieved without them. On £4m and over, D89 needed a Stage 2 LCA report. D88 should have been set up in Stage 1, and D86 depends on whether the lease is still being negotiated. D90 needs Stage 2 and 4 LCA results, so think hard before opting in now.
Most of the score is still open, though. The specifications, the tender documents and the site evidence carry far more measures than the early stages do.
Tell me where you are and I'll tell you what's still achievable.
What does the Net Zero aligned certificate need?
D85 Energy Use Intensity and D90 Embodied Carbon Intensity, both achieved. D90 is an opt-in, needs the D89 LCA at Stages 2 and 4 and the Stage 6 actuals report, and has to meet the UK Net Zero Carbon Buildings Standard upfront limit for the year you start on site.
The certificate comes at whatever rating you achieve, and it's SKA's own. It has no official link to certification under the UK Net Zero Carbon Buildings Standard.
How long after handover do we get the certificate?
SKA says the certification process takes between a couple of days and a few weeks once the assessor has completed the handover assessment, depending on the payment method and how many previews and changes are asked for.
The assessment itself can't finish until the evidence pack is complete, so collect it as you go.
Services
Specialist capacity, without the headcount
Consultancy, contractor or in-house team with more certification work than people to deliver it? I plug in for as long as the work exists across commercial fit-outs and refurbishments. You keep the client. I do the certification work.
Licensed Assessor and AP
BREEAM services
Licensed Assessor for UK New Construction, and AP (Design and Site) from concept design to site.
SKA Assessor
SKA Rating services
Fit-out assessments, from scoping the measures to issuing the certificate.
WELL AP
WELL services
Route, scorecard and documentation, with the submission managed through IWBI review.
Fitwel Ambassador
Fitwel services
Scorecard set-up, evidence and submission, for new and existing buildings.
WiredScore AP
WiredScore services
Gap analysis, target level, evidence pack and improvement advice.
ActiveScore and ModeScore AP
ActiveScore services
Submission, score modelling and the improvements worth making.
Got a SKA project that needs a pair of hands?
Email or call me. Tell me what the project is, where it's up to and which scheme it's after, and attach drawings, a programme or a scope of works if you have them.
- Emailgeorge@welscape.co.uk
- Phone+44 7542 341750