SKArating Offices Environmental 2.0 — RIBA Stage 0–6 Programme
When every deliverable, report and exercise has to happen, assuming all 79 in-programme Good Practice Measures are scoped in and targeted. Diamonds mark the stage by which a report or document must be issued to the team in final form — not when the Assessor submits it.
46 exercises · 79 GPMs · 16 scoped in for all fit-outs · Source: SKArating Offices Environmental Good Practice Measures 2.0
Owner SKA Assessor Main contractor Design team Technical consultants Client / landlord ActivityActiveOngoingIssued — final documentWorkshop / meetingALLScoped in for all fit-outs
SKA good practice measuresRIBA plan of work stage
Exercise / report / deliverableSKA GPM refsOwner 0Strategic Definition 1Preparation & Brief 2Concept Design 3Spatial Coordination 4Technical Design 5Manufacturing & Construction 6Handover & Close-out
Assessment, targeting & project set-up
Scheme selection & rating targetScheme selection & rating target
All GPMs  ·  SKA Assessor (Welscape)
Scheme, target rating and project boundary confirmed in the client brief.
S0 ISSUED
All GPMs SKA Assessor
Pre-assessment workshop & GPM scopingPre-assessment workshop & GPM scoping
All 83 GPMs  ·  SKA Assessor (Welscape)
Workshop the full measure list; issue the scoping & targeting schedule by end of Stage 2.
S1 workshop  ·  S2 ISSUED
All 83 GPMs SKA Assessor
Targets registerTargets register
D85 · D90 · D89 · D28  ·  SKA Assessor (Welscape)
EUI, ECI, embodied carbon and thermal comfort targets set at brief, frozen at Stage 4.
S1 active  ·  S2 ongoing  ·  S3 ongoing  ·  S4 ISSUED
D85 · D90 · D89 · D28 SKA Assessor
ALLSKA project delivery programmeSKA project delivery programme
D88  ·  SKA Assessor (Welscape) · scoped in for all fit-outs
Manual requires this to be established during RIBA Stage 1 and to cover brief through post-completion.
S1 ISSUED  ·  S2 ongoing  ·  S3 ongoing  ·  S4 ongoing  ·  S5 ongoing  ·  S6 ongoing
D88 SKA Assessor
ALLLandlord–tenant energy collaborationLandlord–tenant energy collaboration
D86  ·  Client, landlord & PM · scoped in for all fit-outs
Lease terms can be agreed before the design team is appointed — assume this starts at Stage 0. Workshop then agreed scope of works.
S0 active  ·  S1 workshop  ·  S2 ISSUED  ·  S3 ongoing  ·  S4 ongoing  ·  S5 ongoing  ·  S6 ongoing
D86 Client / landlord
ALLProject sustainability delivery planProject sustainability delivery plan
D44  ·  Main contractor / PCSA · scoped in for all fit-outs
Requirement issued into procurement documents at Stage 4; contractor's plan itself issued pre-construction.
S2 active  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ISSUED  ·  S6 ongoing
D44 Main contractor
DESIGN STAGE assessment reportDESIGN STAGE assessment report
All targeted GPMs  ·  SKA Assessor (Welscape)
Assessor's report on the targeted credits, issued at the end of technical design.
S4 ISSUED
All targeted GPMs SKA Assessor
Pre-contract & subcontractor SKA briefingsPre-contract & subcontractor SKA briefings
D88 · D09 · D07 · D44 · D60  ·  SKA Assessor (Welscape)
Walk the contractor and each subcontractor through every targeted credit and its evidence.
S4 workshop  ·  S5 workshop
D88 · D09 · D07 · D44 · D60 SKA Assessor
Site visits & credits-at-risk reportSite visits & credits-at-risk report
All targeted GPMs  ·  SKA Assessor (Welscape)
Two site visits plus a mid-construction status report flagging credits at risk.
S5 ISSUED
All targeted GPMs SKA Assessor
HANDOVER STAGE assessment reportHANDOVER STAGE assessment report
All targeted GPMs  ·  SKA Assessor (Welscape)
Evidence pack compiled, actuals verified against targets, final rating issued.
S6 ISSUED
All targeted GPMs SKA Assessor
Resource management & waste
ALLPre-refurbishment auditPre-refurbishment audit
D72  ·  Main contractor / PCSA · scoped in for all fit-outs
RIBA 1–2 in the D09 fixed asset management process. Must be issued to the team in final form by end of Stage 2 — it sets every downstream RM decision.
S1 active  ·  S2 ISSUED
D72 Main contractor
ALLWhole Life Resource Optimisation workshopsWhole Life Resource Optimisation workshops
D60  ·  Design team / specifier · scoped in for all fit-outs
RIBA 2 and again at 4/5. Second round runs with the contractor and subcontractors at onboarding; outputs feed the RMPT.
S2 workshop  ·  S3 ongoing  ·  S4 workshop  ·  S5 workshop
D60 Design team
ALLResource Management Plan & Tracker (RMPT)Resource Management Plan & Tracker (RMPT)
D09  ·  Main contractor / PCSA · scoped in for all fit-outs
Spans RIBA 1–6. Set up at Stage 1, Design Stage review at Stage 4, minimum 3-monthly updates on site, final schedule at completion.
S1 active  ·  S2 active  ·  S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D09 Main contractor
RM decisions — fixed fit-out & finishesRM decisions — fixed fit-out & finishes
D12 D13 D74 D14 D34 D48 D46 D68  ·  Main contractor / PCSA
Re-use / take-back / recycle route per product for partitions, ceilings, floors, doors and services. Recorded in the RMPT.
S2 active  ·  S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ongoing
D12 D13 D74 D14 D34 D48 D46 D68 Main contractor
RM decisions — furniture, joinery & HVACRM decisions — furniture, joinery & HVAC
D06 D15 D16 D17 D18 D68  ·  Main contractor / PCSA
Re-use and take-back routes for joinery, desks, chairs, storage, loose furniture and HVAC.
S2 active  ·  S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ongoing
D06 D15 D16 D17 D18 D68 Main contractor
ALLSite Waste Management PlanSite Waste Management Plan
D07  ·  Main contractor / PCSA · scoped in for all fit-outs
A pre-construction document. At design stage it is only a prelims requirement, with unavoidable waste identified in the RMPT. Final SWMP and waste contractor report at completion.
S4 ongoing  ·  S5 ISSUED  ·  S6 ISSUED
D07 Main contractor
ALLPackaging take-back strategy & recordsPackaging take-back strategy & records
D73  ·  Main contractor / PCSA · scoped in for all fit-outs
Take-back routes identified from Stage 2 so they can be written into supplier contracts; quantities reported through the RMPT.
S2 active  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D73 Main contractor
ALLFixed asset tagging & registerFixed asset tagging & register
D84  ·  Main contractor / PCSA · scoped in for all fit-outs
Tagging written into the scope of works at Stage 4; applied on site at Stage 5; register issued to client / FM at handover.
S4 ISSUED  ·  S5 active  ·  S6 ISSUED
D84 Main contractor
Carbon & energy modelling
Operational energy model (CIBSE TM54)Operational energy model (CIBSE TM54)
D66  ·  MEP, energy, LCA & acoustic consultants
Dynamic simulation required above £2m. Design stage model issued at Stage 4, as-built check at Stage 6.
S2 active  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D66 Technical consultants
Energy Use Intensity — target & verificationEnergy Use Intensity — target & verification
D85  ·  MEP, energy, LCA & acoustic consultants
kWh/m²/yr against the UKNZCBS Annex A target for the year of construction.
S1 active  ·  S2 ongoing  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D85 Technical consultants
ALLEmbodied carbon assessment (LCA)Embodied carbon assessment (LCA)
D89  ·  MEP, energy, LCA & acoustic consultants · scoped in for all fit-outs
Reports required at RIBA 2, 4 and 6. Optional only where build cost is £500k or below; below £4m a Stage 6 report alone is permitted.
S2 ISSUED  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D89 Technical consultants
Embodied Carbon IntensityEmbodied Carbon Intensity
D90  ·  MEP, energy, LCA & acoustic consultants
kgCO₂e/m² against UKNZCBS Annex A, reported alongside D89 at RIBA 2, 4 and 6.
S1 active  ·  S2 ISSUED  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D90 Technical consultants
Whole Life Carbon assessmentWhole Life Carbon assessment
D47  ·  MEP, energy, LCA & acoustic consultants
Full A1–C4 assessment reported at RIBA 2, 4 and 6.
S2 ISSUED  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D47 Technical consultants
LCA impact comparisonLCA impact comparison
D87  ·  MEP, energy, LCA & acoustic consultants
Comparative study informing strip-out vs refurbish vs re-use. Runs Stage 2 into Stage 4 as options are optioneered.
S2 active  ·  S3 ongoing  ·  S4 ISSUED
D87 Technical consultants
Energy demand reduction studyEnergy demand reduction study
E29  ·  MEP, energy, LCA & acoustic consultants
Runs Stage 2 into Stage 4 — lighting and services options need optioneering before the design freezes.
S2 active  ·  S3 ongoing  ·  S4 ISSUED
E29 Technical consultants
Energy & water metering strategyEnergy & water metering strategy
E08 · E17  ·  MEP, energy, LCA & acoustic consultants
Sub-metering layout and reporting protocol issued at Stage 4; readings verified at handover.
S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
E08 · E17 Technical consultants
MEP design & specification
Lighting design, efficacy & controlsLighting design, efficacy & controls
D01 · D02 · E04  ·  MEP, energy, LCA & acoustic consultants
Installed power density, control zoning and ETL-listed fittings.
S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D01 · D02 · E04 Technical consultants
Heat pump & ventilation efficiencyHeat pump & ventilation efficiency
E05 · E31  ·  MEP, energy, LCA & acoustic consultants
ETL-listed heat pumps and ventilation equipment confirmed in the schedules.
S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
E05 · E31 Technical consultants
Refrigerant DELC CO₂e & leak preventionRefrigerant DELC CO₂e & leak prevention
D23 · D57  ·  MEP, energy, LCA & acoustic consultants
Technical design items — refrigerant selection and the DELC calculation land at Stage 4, not before. ≤100 kgCO₂e/kW cooling capacity.
S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D23 · D57 Technical consultants
Healthy internal conditions (CIBSE AM11)Healthy internal conditions (CIBSE AM11)
D28  ·  MEP, energy, LCA & acoustic consultants
Thermal comfort modelling plus indoor air quality criteria; verified post-commissioning.
S2 active  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D28 Technical consultants
Plant noise assessment & limitsPlant noise assessment & limits
D25  ·  MEP, energy, LCA & acoustic consultants
Acoustic strategy against background noise targets; verified on site.
S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
D25 Technical consultants
Water fittings, shut-off & leak detectionWater fittings, shut-off & leak detection
E14 · E19 · E20  ·  MEP, energy, LCA & acoustic consultants
Flow rates, sanitary supply shut-off and leak detection specified and installed.
S3 active  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
E14 · E19 · E20 Technical consultants
Materials & product specification
Timber chain-of-custody strategyTimber chain-of-custody strategy
D20  ·  Design team / specifier
Considered from Stage 2 so chain of custody is protected through procurement; the full CoC pack is only issuable once every subcontractor's documentation is in, at end of construction.
S2 active  ·  S3 ongoing  ·  S4 active  ·  S5 ISSUED
D20 Design team
Spec — fixed fit-out & finishesSpec — fixed fit-out & finishes
M06 M18 M08 M10 M07 M17 M04 M03 M13 M16 M11 M12 M14 M23  ·  Design team / specifier
Product families considered from Stage 2; final schedules issued at Stage 4 before construction. Joinery, kitchens, partitions, ceilings, floors, doors, insulation, screed, walls, paints, blinds.
S2 active  ·  S3 active  ·  S4 ISSUED  ·  S5 ongoing
M06 M18 M08 M10 M07 M17 M04 M03 M13 M16 M11 M12 M14 M23 Design team
Spec — furniture & seatingSpec — furniture & seating
M19 · M20 · M21 · M22 · M29  ·  Design team / specifier
Considered from Stage 2; final schedules issued at Stage 4. Desks, task seating, soft seating, storage and other loose furniture.
S2 active  ·  S3 active  ·  S4 ISSUED  ·  S5 ongoing
M19 · M20 · M21 · M22 · M29 Design team
Spec — MEP & lighting productsSpec — MEP & lighting products
M30 · M31 · M32 · M33  ·  Design team / specifier
Follows the MEP technical design rather than the Stage 2 material palette. HVAC equipment, cables/pipes/ducts, light fittings and decorative lighting.
S3 active  ·  S4 ISSUED  ·  S5 ongoing
M30 · M31 · M32 · M33 Design team
Product evidence pack (EPD / PCDS / ETL)Product evidence pack (EPD / PCDS / ETL)
All M-series · D20  ·  Design team / specifier
Certification checked from Stage 2 as products are shortlisted. Design stage pack issued at Stage 4; as-installed pack, covering any substitutions, at handover.
S2 active  ·  S3 ongoing  ·  S4 ISSUED  ·  S5 ongoing  ·  S6 ISSUED
All M-series · D20 Design team
Space planning & layout
Cycle parking, showers & cyclist lockersCycle parking, showers & cyclist lockers
D41 · D42 · D43  ·  Design team / specifier
Floor area reserved at concept and fixed at spatial coordination — cannot be retro-fitted once the plate is committed.
S2 active  ·  S3 ISSUED  ·  S4 ongoing  ·  S5 ongoing  ·  S6 ongoing
D41 · D42 · D43 Design team
Recyclable waste storage spaceRecyclable waste storage space
D08  ·  Design team / specifier
Segregated storage sized and located on the floor plate; layout fixed at Stage 3.
S2 active  ·  S3 ISSUED  ·  S4 ongoing  ·  S5 ongoing  ·  S6 ongoing
D08 Design team
Soft Landings, handover & training
ALLSoft Landings design workshopsSoft Landings design workshops
D69  ·  Design team / specifier · scoped in for all fit-outs
BSRIA Soft Landings starts at RIBA Stage 2. Client, design team, contractor and operators agree operational performance outcomes.
S1 active  ·  S2 workshop  ·  S3 workshop  ·  S4 workshop
D69 Design team
ALLSoft Landings commissioning & trainingSoft Landings commissioning & training
D70  ·  Main contractor / PCSA · scoped in for all fit-outs
Commissioning records, operator training and handover programme.
S4 active  ·  S5 ongoing  ·  S6 ISSUED
D70 Main contractor
ALLBuilding User GuideBuilding User Guide
D45  ·  Main contractor / PCSA · scoped in for all fit-outs
Plain-language occupant and FM guide. Written commitment at design stage, guide issued at handover.
S4 active  ·  S5 ongoing  ·  S6 ISSUED
D45 Main contractor
Construction-phase monitoring
ALLFit-out energy useFit-out energy use
P01  ·  Main contractor / PCSA · scoped in for all fit-outs
Target set at tender, metered through the works, reported at handover.
S4 active  ·  S5 ongoing  ·  S6 ISSUED
P01 Main contractor
ALLFit-out water useFit-out water use
P07  ·  Main contractor / PCSA · scoped in for all fit-outs
Target set at tender, metered through the works, reported at handover.
S4 active  ·  S5 ongoing  ·  S6 ISSUED
P07 Main contractor
ALLConstruction transport CO₂Construction transport CO₂
D59  ·  Main contractor / PCSA · scoped in for all fit-outs
Loads, distance and vehicle class logged for deliveries and waste removal.
S4 active  ·  S5 ongoing  ·  S6 ISSUED
D59 Main contractor
Construction water pollution controlsConstruction water pollution controls
P19  ·  Main contractor / PCSA
Risk plan for wet trades, refrigerant handling and fuel storage; monitored on site.
S4 active  ·  S5 ongoing  ·  S6 ISSUED
P19 Main contractor
Hover any row for what it requires and when.
Stage 2 is the pinch point. Target-setting, the pre-refurbishment audit, space allocation and the first predictive models all land here. Anything missed is usually unrecoverable.
Stage 4 freezes the design for most measures — but not all. D72, D60 and the space-planning measures are constrained earlier and must be issued by Stage 2 or 3; D07, D84 and D20 cannot be closed until pre-construction or later.
Most exercises are not the Assessor's to deliver. The Assessor co-ordinates, reviews against the GPM criteria and submits; MEP, LCA, acoustic consultants and the contractor produce the substance.
Four GPMs sit outside RIBA 0–6. P10 lighting energy in use, P11 small power energy in use, P18 zero carbon energy contracts and the occupancy limb of D71 Soft Landings aftercare are assessed at occupancy stage only, and are excluded.