SKArating Offices Environmental 2.0 — RIBA Stage 0–6 Programme
When every deliverable, report and exercise has to happen, assuming all 79 in-programme Good Practice Measures are scoped in and targeted. Diamonds mark the stage by which a report or document must be issued to the team in final form — not when the Assessor submits it.
Owner
SKA Assessor
Main contractor
Design team
Technical consultants
Client / landlord
ActivityActiveOngoingIssued — final documentWorkshop / meetingALLScoped in for all fit-outs
| SKA good practice measures | RIBA plan of work stage | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| Exercise / report / deliverable | SKA GPM refs | Owner | 0Strategic Definition | 1Preparation & Brief | 2Concept Design | 3Spatial Coordination | 4Technical Design | 5Manufacturing & Construction | 6Handover & Close-out |
| Assessment, targeting & project set-up | |||||||||
| Scheme selection & rating targetScheme selection & rating target All GPMs · SKA Assessor (Welscape) Scheme, target rating and project boundary confirmed in the client brief.S0 ISSUED |
All GPMs | SKA Assessor | |||||||
| Pre-assessment workshop & GPM scopingPre-assessment workshop & GPM scoping All 83 GPMs · SKA Assessor (Welscape) Workshop the full measure list; issue the scoping & targeting schedule by end of Stage 2.S1 workshop · S2 ISSUED |
All 83 GPMs | SKA Assessor | |||||||
| Targets registerTargets register D85 · D90 · D89 · D28 · SKA Assessor (Welscape) EUI, ECI, embodied carbon and thermal comfort targets set at brief, frozen at Stage 4.S1 active · S2 ongoing · S3 ongoing · S4 ISSUED |
D85 · D90 · D89 · D28 | SKA Assessor | |||||||
| ALLSKA project delivery programmeSKA project delivery programme D88 · SKA Assessor (Welscape) · scoped in for all fit-outs Manual requires this to be established during RIBA Stage 1 and to cover brief through post-completion.S1 ISSUED · S2 ongoing · S3 ongoing · S4 ongoing · S5 ongoing · S6 ongoing |
D88 | SKA Assessor | |||||||
| ALLLandlord–tenant energy collaborationLandlord–tenant energy collaboration D86 · Client, landlord & PM · scoped in for all fit-outs Lease terms can be agreed before the design team is appointed — assume this starts at Stage 0. Workshop then agreed scope of works.S0 active · S1 workshop · S2 ISSUED · S3 ongoing · S4 ongoing · S5 ongoing · S6 ongoing |
D86 | Client / landlord | |||||||
| ALLProject sustainability delivery planProject sustainability delivery plan D44 · Main contractor / PCSA · scoped in for all fit-outs Requirement issued into procurement documents at Stage 4; contractor's plan itself issued pre-construction.S2 active · S3 ongoing · S4 ISSUED · S5 ISSUED · S6 ongoing |
D44 | Main contractor | |||||||
| DESIGN STAGE assessment reportDESIGN STAGE assessment report All targeted GPMs · SKA Assessor (Welscape) Assessor's report on the targeted credits, issued at the end of technical design.S4 ISSUED |
All targeted GPMs | SKA Assessor | |||||||
| Pre-contract & subcontractor SKA briefingsPre-contract & subcontractor SKA briefings D88 · D09 · D07 · D44 · D60 · SKA Assessor (Welscape) Walk the contractor and each subcontractor through every targeted credit and its evidence.S4 workshop · S5 workshop |
D88 · D09 · D07 · D44 · D60 | SKA Assessor | |||||||
| Site visits & credits-at-risk reportSite visits & credits-at-risk report All targeted GPMs · SKA Assessor (Welscape) Two site visits plus a mid-construction status report flagging credits at risk.S5 ISSUED |
All targeted GPMs | SKA Assessor | |||||||
| HANDOVER STAGE assessment reportHANDOVER STAGE assessment report All targeted GPMs · SKA Assessor (Welscape) Evidence pack compiled, actuals verified against targets, final rating issued.S6 ISSUED |
All targeted GPMs | SKA Assessor | |||||||
| Resource management & waste | |||||||||
| ALLPre-refurbishment auditPre-refurbishment audit D72 · Main contractor / PCSA · scoped in for all fit-outs RIBA 1–2 in the D09 fixed asset management process. Must be issued to the team in final form by end of Stage 2 — it sets every downstream RM decision.S1 active · S2 ISSUED |
D72 | Main contractor | |||||||
| ALLWhole Life Resource Optimisation workshopsWhole Life Resource Optimisation workshops D60 · Design team / specifier · scoped in for all fit-outs RIBA 2 and again at 4/5. Second round runs with the contractor and subcontractors at onboarding; outputs feed the RMPT.S2 workshop · S3 ongoing · S4 workshop · S5 workshop |
D60 | Design team | |||||||
| ALLResource Management Plan & Tracker (RMPT)Resource Management Plan & Tracker (RMPT) D09 · Main contractor / PCSA · scoped in for all fit-outs Spans RIBA 1–6. Set up at Stage 1, Design Stage review at Stage 4, minimum 3-monthly updates on site, final schedule at completion.S1 active · S2 active · S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D09 | Main contractor | |||||||
| RM decisions — fixed fit-out & finishesRM decisions — fixed fit-out & finishes D12 D13 D74 D14 D34 D48 D46 D68 · Main contractor / PCSA Re-use / take-back / recycle route per product for partitions, ceilings, floors, doors and services. Recorded in the RMPT.S2 active · S3 active · S4 ISSUED · S5 ongoing · S6 ongoing |
D12 D13 D74 D14 D34 D48 D46 D68 | Main contractor | |||||||
| RM decisions — furniture, joinery & HVACRM decisions — furniture, joinery & HVAC D06 D15 D16 D17 D18 D68 · Main contractor / PCSA Re-use and take-back routes for joinery, desks, chairs, storage, loose furniture and HVAC.S2 active · S3 active · S4 ISSUED · S5 ongoing · S6 ongoing |
D06 D15 D16 D17 D18 D68 | Main contractor | |||||||
| ALLSite Waste Management PlanSite Waste Management Plan D07 · Main contractor / PCSA · scoped in for all fit-outs A pre-construction document. At design stage it is only a prelims requirement, with unavoidable waste identified in the RMPT. Final SWMP and waste contractor report at completion.S4 ongoing · S5 ISSUED · S6 ISSUED |
D07 | Main contractor | |||||||
| ALLPackaging take-back strategy & recordsPackaging take-back strategy & records D73 · Main contractor / PCSA · scoped in for all fit-outs Take-back routes identified from Stage 2 so they can be written into supplier contracts; quantities reported through the RMPT.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D73 | Main contractor | |||||||
| ALLFixed asset tagging & registerFixed asset tagging & register D84 · Main contractor / PCSA · scoped in for all fit-outs Tagging written into the scope of works at Stage 4; applied on site at Stage 5; register issued to client / FM at handover.S4 ISSUED · S5 active · S6 ISSUED |
D84 | Main contractor | |||||||
| Carbon & energy modelling | |||||||||
| Operational energy model (CIBSE TM54)Operational energy model (CIBSE TM54) D66 · MEP, energy, LCA & acoustic consultants Dynamic simulation required above £2m. Design stage model issued at Stage 4, as-built check at Stage 6.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D66 | Technical consultants | |||||||
| Energy Use Intensity — target & verificationEnergy Use Intensity — target & verification D85 · MEP, energy, LCA & acoustic consultants kWh/m²/yr against the UKNZCBS Annex A target for the year of construction.S1 active · S2 ongoing · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D85 | Technical consultants | |||||||
| ALLEmbodied carbon assessment (LCA)Embodied carbon assessment (LCA) D89 · MEP, energy, LCA & acoustic consultants · scoped in for all fit-outs Reports required at RIBA 2, 4 and 6. Optional only where build cost is £500k or below; below £4m a Stage 6 report alone is permitted.S2 ISSUED · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D89 | Technical consultants | |||||||
| Embodied Carbon IntensityEmbodied Carbon Intensity D90 · MEP, energy, LCA & acoustic consultants kgCO₂e/m² against UKNZCBS Annex A, reported alongside D89 at RIBA 2, 4 and 6.S1 active · S2 ISSUED · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D90 | Technical consultants | |||||||
| Whole Life Carbon assessmentWhole Life Carbon assessment D47 · MEP, energy, LCA & acoustic consultants Full A1–C4 assessment reported at RIBA 2, 4 and 6.S2 ISSUED · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D47 | Technical consultants | |||||||
| LCA impact comparisonLCA impact comparison D87 · MEP, energy, LCA & acoustic consultants Comparative study informing strip-out vs refurbish vs re-use. Runs Stage 2 into Stage 4 as options are optioneered.S2 active · S3 ongoing · S4 ISSUED |
D87 | Technical consultants | |||||||
| Energy demand reduction studyEnergy demand reduction study E29 · MEP, energy, LCA & acoustic consultants Runs Stage 2 into Stage 4 — lighting and services options need optioneering before the design freezes.S2 active · S3 ongoing · S4 ISSUED |
E29 | Technical consultants | |||||||
| Energy & water metering strategyEnergy & water metering strategy E08 · E17 · MEP, energy, LCA & acoustic consultants Sub-metering layout and reporting protocol issued at Stage 4; readings verified at handover.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E08 · E17 | Technical consultants | |||||||
| MEP design & specification | |||||||||
| Lighting design, efficacy & controlsLighting design, efficacy & controls D01 · D02 · E04 · MEP, energy, LCA & acoustic consultants Installed power density, control zoning and ETL-listed fittings.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D01 · D02 · E04 | Technical consultants | |||||||
| Heat pump & ventilation efficiencyHeat pump & ventilation efficiency E05 · E31 · MEP, energy, LCA & acoustic consultants ETL-listed heat pumps and ventilation equipment confirmed in the schedules.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E05 · E31 | Technical consultants | |||||||
| Refrigerant DELC CO₂e & leak preventionRefrigerant DELC CO₂e & leak prevention D23 · D57 · MEP, energy, LCA & acoustic consultants Technical design items — refrigerant selection and the DELC calculation land at Stage 4, not before. ≤100 kgCO₂e/kW cooling capacity.S4 ISSUED · S5 ongoing · S6 ISSUED |
D23 · D57 | Technical consultants | |||||||
| Healthy internal conditions (CIBSE AM11)Healthy internal conditions (CIBSE AM11) D28 · MEP, energy, LCA & acoustic consultants Thermal comfort modelling plus indoor air quality criteria; verified post-commissioning.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
D28 | Technical consultants | |||||||
| Plant noise assessment & limitsPlant noise assessment & limits D25 · MEP, energy, LCA & acoustic consultants Acoustic strategy against background noise targets; verified on site.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
D25 | Technical consultants | |||||||
| Water fittings, shut-off & leak detectionWater fittings, shut-off & leak detection E14 · E19 · E20 · MEP, energy, LCA & acoustic consultants Flow rates, sanitary supply shut-off and leak detection specified and installed.S3 active · S4 ISSUED · S5 ongoing · S6 ISSUED |
E14 · E19 · E20 | Technical consultants | |||||||
| Materials & product specification | |||||||||
| Timber chain-of-custody strategyTimber chain-of-custody strategy D20 · Design team / specifier Considered from Stage 2 so chain of custody is protected through procurement; the full CoC pack is only issuable once every subcontractor's documentation is in, at end of construction.S2 active · S3 ongoing · S4 active · S5 ISSUED |
D20 | Design team | |||||||
| Spec — fixed fit-out & finishesSpec — fixed fit-out & finishes M06 M18 M08 M10 M07 M17 M04 M03 M13 M16 M11 M12 M14 M23 · Design team / specifier Product families considered from Stage 2; final schedules issued at Stage 4 before construction. Joinery, kitchens, partitions, ceilings, floors, doors, insulation, screed, walls, paints, blinds.S2 active · S3 active · S4 ISSUED · S5 ongoing |
M06 M18 M08 M10 M07 M17 M04 M03 M13 M16 M11 M12 M14 M23 | Design team | |||||||
| Spec — furniture & seatingSpec — furniture & seating M19 · M20 · M21 · M22 · M29 · Design team / specifier Considered from Stage 2; final schedules issued at Stage 4. Desks, task seating, soft seating, storage and other loose furniture.S2 active · S3 active · S4 ISSUED · S5 ongoing |
M19 · M20 · M21 · M22 · M29 | Design team | |||||||
| Spec — MEP & lighting productsSpec — MEP & lighting products M30 · M31 · M32 · M33 · Design team / specifier Follows the MEP technical design rather than the Stage 2 material palette. HVAC equipment, cables/pipes/ducts, light fittings and decorative lighting.S3 active · S4 ISSUED · S5 ongoing |
M30 · M31 · M32 · M33 | Design team | |||||||
| Product evidence pack (EPD / PCDS / ETL)Product evidence pack (EPD / PCDS / ETL) All M-series · D20 · Design team / specifier Certification checked from Stage 2 as products are shortlisted. Design stage pack issued at Stage 4; as-installed pack, covering any substitutions, at handover.S2 active · S3 ongoing · S4 ISSUED · S5 ongoing · S6 ISSUED |
All M-series · D20 | Design team | |||||||
| Space planning & layout | |||||||||
| Cycle parking, showers & cyclist lockersCycle parking, showers & cyclist lockers D41 · D42 · D43 · Design team / specifier Floor area reserved at concept and fixed at spatial coordination — cannot be retro-fitted once the plate is committed.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ongoing |
D41 · D42 · D43 | Design team | |||||||
| Recyclable waste storage spaceRecyclable waste storage space D08 · Design team / specifier Segregated storage sized and located on the floor plate; layout fixed at Stage 3.S2 active · S3 ISSUED · S4 ongoing · S5 ongoing · S6 ongoing |
D08 | Design team | |||||||
| Soft Landings, handover & training | |||||||||
| ALLSoft Landings design workshopsSoft Landings design workshops D69 · Design team / specifier · scoped in for all fit-outs BSRIA Soft Landings starts at RIBA Stage 2. Client, design team, contractor and operators agree operational performance outcomes.S1 active · S2 workshop · S3 workshop · S4 workshop |
D69 | Design team | |||||||
| ALLSoft Landings commissioning & trainingSoft Landings commissioning & training D70 · Main contractor / PCSA · scoped in for all fit-outs Commissioning records, operator training and handover programme.S4 active · S5 ongoing · S6 ISSUED |
D70 | Main contractor | |||||||
| ALLBuilding User GuideBuilding User Guide D45 · Main contractor / PCSA · scoped in for all fit-outs Plain-language occupant and FM guide. Written commitment at design stage, guide issued at handover.S4 active · S5 ongoing · S6 ISSUED |
D45 | Main contractor | |||||||
| Construction-phase monitoring | |||||||||
| ALLFit-out energy useFit-out energy use P01 · Main contractor / PCSA · scoped in for all fit-outs Target set at tender, metered through the works, reported at handover.S4 active · S5 ongoing · S6 ISSUED |
P01 | Main contractor | |||||||
| ALLFit-out water useFit-out water use P07 · Main contractor / PCSA · scoped in for all fit-outs Target set at tender, metered through the works, reported at handover.S4 active · S5 ongoing · S6 ISSUED |
P07 | Main contractor | |||||||
| ALLConstruction transport CO₂Construction transport CO₂ D59 · Main contractor / PCSA · scoped in for all fit-outs Loads, distance and vehicle class logged for deliveries and waste removal.S4 active · S5 ongoing · S6 ISSUED |
D59 | Main contractor | |||||||
| Construction water pollution controlsConstruction water pollution controls P19 · Main contractor / PCSA Risk plan for wet trades, refrigerant handling and fuel storage; monitored on site.S4 active · S5 ongoing · S6 ISSUED |
P19 | Main contractor | |||||||
Hover any row for what it requires and when.
Stage 2 is the pinch point. Target-setting, the pre-refurbishment audit, space allocation and the first predictive models all land here. Anything missed is usually unrecoverable.
Stage 4 freezes the design for most measures — but not all. D72, D60 and the space-planning measures are constrained earlier and must be issued by Stage 2 or 3; D07, D84 and D20 cannot be closed until pre-construction or later.
Most exercises are not the Assessor's to deliver. The Assessor co-ordinates, reviews against the GPM criteria and submits; MEP, LCA, acoustic consultants and the contractor produce the substance.
Four GPMs sit outside RIBA 0–6. P10 lighting energy in use, P11 small power energy in use, P18 zero carbon energy contracts and the occupancy limb of D71 Soft Landings aftercare are assessed at occupancy stage only, and are excluded.