SKA Offices 2.0, stage by stage

What's due when, and what it costs to miss it

This is how I run a SKA Offices Environmental 2.0 assessment, laid out against the RIBA stages. For each piece of work it says what has to happen, by when, who usually does it and roughly what kind of cost it is.

It's built from SKA's Good Practice Measures 2.0. Where a measure sets its own deadline, the roadmap says so. Where it doesn't, I've put the work where it needs to happen for the evidence to exist, and marked it as mine.

  • 83measures in Offices 2.0, across nine categories
  • 16apply to every fit-out, whatever its scope
  • 3are only assessed at the optional occupancy stage

How the score works

SKA rates a project on the share of its in-scope measures that are achieved: 25% and above for Bronze, 50% for Silver and 75% for Gold. So the count matters as much as the measures.

SKA also ranks every measure by impact. Earlier versions of the scheme made each rating include some of the top-ranked measures, known as gateway measures, so I confirm any gateway requirements for your project at scoping.

Scope sets the count

Measures come into scope by what the works include, and SKA audits assessors on scoping. You can't drop one that applies. The only choices are the opt-ins: D47, D87, D90 and E29, plus D89 at £500k or less and D08 on a Cat A fit-out. One oddity: D84 applies to every fit-out, but D09's criteria call it optional at £2m or less, so I confirm how it's treated on each project.

Sixteen are always in

They apply to every fit-out, so they're in your count whether you plan for them or not. Most are workshops, plans and records. Add D89, the embodied carbon LCA, unless the build cost is £500k or below.

Some can't be recovered

The pre-refurbishment audit has to be done during Concept Design and isn't re-assessed at handover. D86 happens before the lease is agreed. D07 has to be in the tender before contractors are picked. Lighting sub-metering decides P10 at occupancy. And D09 needs D72, D60 and D07, so losing any of them loses D09 as well.

The count at each threshold

In scopeBronzeSilverGold
40102030
50132538
60153045
70183553

Rounded up. SKA rates a project on the share of in-scope measures achieved: 25% and above for Bronze, 50% for Silver and 75% for Gold.

Opting in cuts both ways. At 30 of 40 measures you're on 75%, the Gold line. Opt into D90, miss the limit, and 30 of 41 is 73%.

The sixteen every fit-out carries

Plan these from day one. They're cheap to win and they cost you points whether you try or not. Each tile shows when it's due, or when I'd do it.

  • D86

    Landlord and tenant collaboration

    Before the agreement for lease

  • D88

    Project delivery programme

    Set up during Stage 1

  • D09

    Resource Management Plan and Tracker

    Stage 1 or 2 to handover, and needs D72, D60 and D07

  • D72

    Pre-refurbishment audit

    During Concept Design

  • D60

    Design for whole life resource optimisation

    Workshops at concept and subcontractor onboarding

  • D69

    Soft Landings design workshops

    Design team and contractor workshops, targets checked in use

  • D44

    Project sustainability delivery plan

    In the tender, then on site

  • D07

    Site Waste Management Plan

    In the tender, written before site starts

  • D73

    Packaging

    Suppliers lined up in the tender

  • D84

    Fixed asset tagging and register

    Tags in the scope, register at handover

  • D59

    Construction transport CO₂

    Travel plan at design, tracked on site

  • P01

    Fit-out energy use

    Readings at least fortnightly

  • P07

    Fit-out water use

    Readings at least fortnightly

  • D70

    Soft Landings commissioning, handover and training

    Commissioning manager during design

  • D71

    Soft Landings aftercare

    Contract at design, aftercare schedule at handover

  • D45

    Building User Guide

    Writer contracted at design, guide at handover

The roadmap, stage by stage

Every measure in Offices 2.0 sits somewhere on this list. Each item says what to do, when, who usually does it and what kind of cost it is.

Deadline set by the measure itself

When I would do it

  1. RIBA Stage 0: Strategic Definition

    Before there's a brief. Only one measure can be lost this early, and it's an easy one to lose.

    • Suggested timing: At the start

      Pick the scheme, the target and the boundary

      Confirm Offices 2.0 fits the space, agree the rating you're after and fix what's inside the project boundary. SKA's online tool is free, so the project can be registered and scoped before anyone's appointed.

      Who
      Client and me
      Cost
      Team time
    • Deadline set by the scheme: Before the agreement for lease is finalised

      Landlord and tenant energy workshop

      D86

      A workshop with the landlord on cutting energy and carbon across both demises for the length of the tenancy, end-of-lease dilapidations included. The actions go into the landlord's or tenant's works and into the agreement for lease.

      If it slips: The GPM ties the workshop to the lease negotiations and offers no other route. If the lease is already signed, raise it at the start.

      Who
      Client and landlord
      Cost
      Team time
  2. RIBA Stage 1: Preparation and Briefing

    Set up the two documents everything else hangs off, and decide which optional measures you're going for.

    • Deadline set by the scheme: During Stage 1

      SKA project delivery programme

      D88

      One programme from brief to post-completion. It has to show when the surveys and resource workshops happen, time to procure reused products, disassembly and storage during the works, and the post-occupancy reviews.

      If it slips: The criteria say it's set up during Stage 1, so it can't wait for the contractor's programme.

      Who
      Client's project manager, with me
      Cost
      Team time
    • Deadline set by the scheme: Set up in Stage 1 or 2

      Resource Management Plan and Tracker (RMPT)

      D09

      The schedule that follows every existing and new material from the audit to where it ends up, with estimated and actual quantities and a named owner for each action. It's reviewed at the design stage and again at handover.

      If it slips: D09 can only be achieved if D72, D60 and D07 are achieved, and D84 too on projects over £2m. Lose one of those and D09 goes with it.

      Who
      Whoever leads resource management, often the contractor under a PCSA
      Cost
      Team time
    • Suggested timing: Before Concept Design

      Decide the opt-in measures

      D90D47D87E29

      Four measures only count if you choose them: Embodied Carbon Intensity, whole life carbon, the LCA comparison and the energy demand study. D89 is optional too at £500k or less, and so is D08 on a Cat A fit-out. Each one you take on adds a measure to the in-scope count, so only take on the ones you'll achieve. D90 with D85 is what unlocks SKA's Net Zero aligned certificate.

      Who
      Client, with me
      Cost
      Team time
    • Suggested timing: Before Concept Design

      Book the carbon and energy specialists

      D89D66

      On projects of £4m and over, D89 needs a predictive LCA at Stage 2, so the LCA consultant has to be on board before Concept Design. D66 needs a CIBSE TM54 energy forecast: dynamic simulation over £2m, steady state allowed below.

      Who
      Client
      Cost
      Specialist fee
  3. RIBA Stage 2: Concept Design

    The pinch point. The audit, the first resource workshop, the Soft Landings targets and the first LCA all happen here, and the audit can't be done later.

    • Deadline set by the scheme: During Concept Design

      Pre-refurbishment audit

      D72

      An experienced designer or other competent person surveys what's there: ceilings, wall and floor finishes, raised floors, partitions, doors, joinery and kitchens, furniture (including what the client already owns), light fittings and controls, and M&E. It records quantities, estimates the waste if it were all thrown away, and identifies what can be kept or reused.

      If it slips: It isn't re-assessed at handover, so once Concept Design has passed it's lost, and D09 goes with it. The other resource management measures are checked against what the audit lists, so they get harder.

      Who
      Design team or other competent person
      Cost
      Team time
    • Deadline set by the scheme: One workshop during Concept Design

      First resource optimisation workshop

      D60

      Work through SKA's design principles with the design team and direct suppliers, from avoiding unnecessary work to designing for repair and disassembly and reusing what's already there. Every decision goes into the RMPT.

      If it slips: D60 needs two workshops, this one and another at subcontractor onboarding. Skip either and D60 fails, and so does D09.

      Who
      Design team and direct suppliers
      Cost
      Team time
    • Suggested timing: From Stage 2

      Soft Landings design workshop

      D69

      The design team, the contractor if appointed, an end-user representative and whoever will run the space. Review lessons from past projects, set roles and set specific, measurable performance targets, such as in-use energy. D69 also needs a design intent workshop with the contractor once they're on board.

      If it slips: Both workshops are required. Handover checks the systems can hit the targets and occupancy checks they did, so vague targets come back to bite.

      Who
      Design team, client and facilities team
      Cost
      Team time
    • Deadline set by the scheme: Stage 2 report

      Embodied carbon LCA, first report

      D89D90D47

      A predictive upfront carbon LCA of the whole scope of works, direct purchases included, to the RICS whole life carbon methodology. On £4m and over it's Stages 2 and 4 plus an as-built report at Stage 6. Under £4m you can do Stages 2 and 4, or Stage 6 only. With D90, the Stage 2 and 4 results have to meet the UK Net Zero Carbon Buildings Standard upfront limit for the year you start on site. D47 runs the same stages over the whole life cycle.

      If it slips: On £4m and over a missed Stage 2 report can't be made up later.

      Who
      LCA consultant
      Cost
      Specialist fee
    • Suggested timing: While the options are open

      Energy and carbon options studies, if chosen

      E29D87

      E29 is an options study on cutting operational energy: daylight, heating and cooling demand, natural or mixed-mode ventilation and plant efficiency. D87 compares the whole life carbon of at least four of five elements: keeping or replacing light fittings, partition types, suspended ceiling against open soffit with baffles, pods against cellular rooms, and one more of your choice.

      Who
      Energy modeller and LCA consultant
      Cost
      Specialist fee
  4. RIBA Stage 3: Spatial Coordination

    The plan gets fixed. Anything that needs floor area or a meter has to be on the drawings now.

    • Suggested timing: Fix on the plan

      Cycle parking, showers, lockers and the recycling store

      D41D42D43D08

      One cycle space per 100 m² of net internal area, or per 10 people if the occupancy is known. One shower per 100 non-transient occupants. One keyless locker per 8 staff. A recycling store sized from an operational waste strategy for the occupier.

      If it slips: These take floor area, and adding them once the layout's coordinated means moving things.

      Who
      Design team
      Cost
      Floor space
    • Suggested timing: Design to it

      Lighting design

      D01D02E04

      300 to 500 lux in continuously occupied areas and 100 lux front and back of house, inside SKA's LENI energy limits. Automatic presence and daylight control, separate perimeter and central zones, and zones that follow the layout. Every fitting on the Energy Technology List or meeting its criteria.

      Who
      Lighting designer or M&E engineer
      Cost
      Specification
    • Suggested timing: Design it in

      Energy and water metering

      E08E17P10

      Energy sub-metered by end use, lighting and small power included, on a system that meets the Energy Technology List criteria. A pulse water meter on the tenant's supply and sub-meters on big users such as a kitchen or gym changing, all reporting to a data logger or BMS.

      If it slips: If D01, D02 or E04 are in scope, P10 comes into scope at the occupancy stage. Without lighting sub-metering it stays in scope but can't be achieved.

      Who
      M&E engineer
      Cost
      Installed kit
    • Suggested timing: If new plant makes external noise

      Plant noise

      D25

      A BS 4142 noise impact assessment, yours or one the landlord already holds, or a report showing new plant stays within 5 dB of background or setting out the attenuation that gets it there. Either way the installed plant has to match the report and a qualified acoustic consultant has to confirm it.

      Who
      Acoustic consultant
      Cost
      Specialist fee
    • Suggested timing: Design to it

      Healthy internal conditions

      D28

      Ventilation rates and comfort conditions to the CIBSE Guide A minimums and lux levels to the CIBSE Code for Lighting, wherever ventilation, heating, cooling or lighting are changed.

      Who
      M&E engineer
      Cost
      Team time
  5. RIBA Stage 4: Technical Design

    Most measures are won or lost in the specification and the tender documents. My design stage assessment comes at the end of this stage.

    • Suggested timing: In every specification

      Specify every product to its criteria

      M03M04M06M07M08M10M11M12M13M14M16M17M18M19M20M21M22M23M29M30M31M32M33D20

      Most materials measures work the same way: each product is reused, or comes from a manufacturer's closed-loop take-back scheme with a Product Circularity Data Sheet, or is new and meets one of the listed routes, such as an upfront carbon limit, an EPD or a recognised certification. Most also need a disassembly guide with every product, and light fittings need a demountability guide. Watch the exceptions: light fittings (M32) and cables, pipes, ducts and controls (M31) need a reused or take-back share as well as compliant new products, and screed and paints have no reuse route. All timber, furniture included, must be reclaimed or come with certified chain of custody to site. Furniture the client buys direct is in scope too.

      If it slips: Specifications are checked at design stage and delivery notes at handover, so a substitution on site can lose a measure you'd already banked.

      Who
      Designer, specifier and furniture supplier
      Cost
      Specification
    • Suggested timing: In the M&E specification

      Plant, refrigerants and leaks

      E05E31M30D23D57

      Heat pumps and heat recovery units on the Energy Technology List or meeting its criteria. Refrigerant systems at no more than 1,000 kgCO₂e per kW of cooling capacity, shown by a DELC calculation to BS EN 378-1 from the manufacturer or installer. Leak prevention to BS EN 378-1 and REAL Zero guidance written into the specification.

      Who
      M&E engineer
      Cost
      Specification
    • Suggested timing: In the specification

      Water fittings

      E14E19E20

      Taps, cleaners' sinks aside, at 4 litres a minute or less up to 5 bar, with a Unified Water Label, and auto shut-off within 20 seconds where it's fitted. A shut-off on the washroom cold supply when nobody's in, and a leak detection system with an adjustable alarm.

      Who
      M&E engineer
      Cost
      Installed kit
    • Suggested timing: By the design stage assessment

      Energy model and Energy Use Intensity

      D66D85

      A CIBSE TM54 forecast of the fitted-out space in kWh/m² a year, using base build data where you can get it. D85 compares it with the UK Net Zero Carbon Buildings Standard limit for the year the fit-out starts on site, from the Annex A table that matches the base build.

      If it slips: D85 can't be achieved without the D66 model, and both are checked again at handover against the as-built drawings.

      Who
      Energy modeller
      Cost
      Specialist fee
    • Deadline set by the scheme: Stage 4 report

      Embodied carbon LCA, second report

      D89D90D47

      The predictive LCA updated for the technical design. With D90, this is the report that shows whether you're inside the limit before anything's bought.

      Who
      LCA consultant
      Cost
      Specialist fee
    • Deadline set by the scheme: Before contractors are selected

      Waste plan requirements in the tender

      D07

      The project requirements sent to tenderers include all of D07's criteria: a Site Waste Management Plan targeting 95% diversion from landfill of unavoidable non-hazardous waste, and a licensed waste contractor certified to PAS 402 or providing the same data.

      If it slips: D07 is checked against what went to contractors before they were picked. Add it after award and it's lost, and D09 with it.

      Who
      Client's project manager or cost consultant, with me
      Cost
      Team time
    • Suggested timing: In the tender

      The rest of SKA in the tender

      D44D73P01P07P19D84D60D59

      D44, D73, P01 and P07 are checked against the procurement information, so the tender asks for a construction environmental and sustainability plan; returnable packaging from at least four of plasterboard and dry lining, timber sheet, glass, paint, joinery, furniture and light fittings; and energy and water metered on site at least fortnightly, with at least five readings. Water pollution controls, an ID tag on every item installed or adapted, and subcontractors at a resource workshop are easiest to secure there too. A design-stage travel plan estimates the transport emissions of deliveries and waste.

      Who
      Client's project manager or cost consultant, with me
      Cost
      Team time
    • Deadline set by the scheme: During design

      Commissioning manager, aftercare and the user guide

      D70D71D45

      The contractor's commissioning manager appointed during the design stage. A contract or client commitment for the designer and contractor to come back and fine-tune through the first year, with a named point of contact. And a named organisation contracted to write the Building User Guide.

      If it slips: If the contractor won't be appointed until after Stage 4, talk to me early about how D70 can still be met.

      Who
      Client
      Cost
      Team time
    • Suggested timing: Record in the RMPT

      Reuse decisions for everything that's coming out

      D06D12D13D14D15D16D17D18D34D38D46D48D68D74

      For each existing item in the audit, record where it's going: reused here or on another project, back to the manufacturer for closed-loop recycling, or diverted from landfill. Most have their own minimum, for example 40% of removed partitions and ceilings and 50% of removed light fittings reused or taken back. Reused items need a Product Circularity Data Sheet.

      Who
      Contractor and design team
      Cost
      Team time
    • Suggested timing: End of Stage 4

      Design stage assessment

      I check the drawings, specifications, calculations and commitments against every targeted measure and report what's achieved, what's at risk and what's needed from whom.

      Who
      Me
  6. RIBA Stage 5: Manufacturing and Construction

    Evidence gets made or lost on site. Most of it is paperwork that's easy to collect at the time and painful to rebuild later.

    • Suggested timing: On contractor appointment

      Design intent workshop with the contractor

      D69

      The second D69 workshop: take the contractor through the design intent and the Soft Landings performance targets.

      If it slips: Skip it and D69 fails, however good the design workshop was.

      Who
      Design team and contractor
      Cost
      Team time
    • Deadline set by the scheme: During subcontractor onboarding

      Second resource optimisation workshop

      D60

      Take the subcontractors through the same design principles and update the RMPT with what they commit to.

      If it slips: Without it D60 isn't achieved, however good the first workshop was.

      Who
      Contractor and subcontractors
      Cost
      Team time
    • Deadline set by the scheme: Before site works start

      Site Waste Management Plan

      D07

      The contractor's SWMP, tied to the unavoidable waste streams in the RMPT, with the 95% diversion target, projected quantities and a licensed waste contractor certified to PAS 402 or providing the same data.

      Who
      Contractor
      Cost
      Team time
    • Deadline set by the scheme: At least every three months

      Keep the RMPT live

      D09

      Handed to a named manager in the construction team and updated at least once in every three-month period, with the SWMP's waste streams and quantities.

      Who
      Contractor
      Cost
      Team time
    • Deadline set by the scheme: At least fortnightly

      Meter readings and site records

      P01P07D59P19

      Energy and water meter readings at least once a fortnight, at least five over the job. Delivery and waste vehicle movements tracked against the travel plan. Wash water from paints, plaster, screed, grout and adhesives filtered and pH-treated, commissioning water treated, and records kept.

      Who
      Contractor
      Cost
      Team time
    • Suggested timing: As products arrive

      Delivery notes and chain of custody

      D20

      Every delivery note or invoice for new or recycled timber needs the supplier's name and dispatch depot, quantities, the product, the claim (70% Mix at least) and the chain of custody certificate number. Furniture can show chain of custody to the supplier's consolidation store plus its delivery note to site. Keep delivery notes for every specified product, and check substitutions against the specification before they're ordered.

      Who
      Contractor and suppliers
      Cost
      Team time
    • Suggested timing: Throughout

      Packaging back, tags on

      D73D84

      Returnable packaging goes back to the suppliers. All single-use plastic packaging is recorded in the RMPT and SWMP and segregated for recycling. Asset tags go onto every item installed or adapted.

      Who
      Contractor
      Cost
      Team time
    • Deadline set by the scheme: Before handover

      Commissioning and training

      D70

      Operators trained through their involvement in commissioning and testing, and a short commissioning report written for them.

      Who
      Contractor's commissioning manager
      Cost
      Team time
    • Suggested timing: Usually twice

      My site visits

      I normally visit twice and send a mid-construction report on measures at risk, while there's still time to fix them.

      Who
      Me
  7. RIBA Stage 6: Handover

    Certification starts here, once the evidence pack is complete.

    • Deadline set by the scheme: Stage 6 report

      As-built LCA

      D89D90D47

      The LCA as delivered, for projects of £4m and over or on the Stage 6 route, submitted to the Built Environment Carbon Database. SKA's handover check asks for evidence of upload for each stage, so upload the Stage 2 and 4 data too. D90 is checked against the Stage 6 actuals report, so plan for one if you've opted in, whichever route D89 took.

      Who
      LCA consultant
      Cost
      Specialist fee
    • Deadline set by the scheme: At completion

      Final waste and resource records

      D07D09D84

      The final SWMP and the waste contractor's report, showing 95% of unavoidable non-hazardous waste diverted from landfill. The final RMPT with actual quantities and destinations. The asset register, set up or updated for the occupier's facilities team, linking each tag to the material, manufacturer, warranty, installation date and location, the EPD or PCDS, data sheet, deconstruction guide and end-of-life requirements.

      Who
      Contractor
      Cost
      Team time
    • Deadline set by the scheme: At handover

      User guide, training records and handover information

      D45D70

      Building User Guides for the facilities manager and the occupants, in plain language. Signed training records, the commissioning summary, and handover information in the format agreed in the handover plan.

      Who
      Contractor
      Cost
      Team time
    • Deadline set by the scheme: At handover

      Aftercare in place

      D71

      A Soft Landings responsibilities schedule naming the point of contact, with time on site for walkabouts through the first 8 weeks of occupation: at least a day a week, or a day a fortnight under £2m. And the contractor appointed to validate sub-meter readings after 2 or 3 months of operation.

      If it slips: The occupancy stage is optional, so on most projects this is the evidence that decides D71.

      Who
      Client, design team and contractor
      Cost
      Team time
    • Deadline set by the scheme: At completion

      Fit-out energy and water totals

      P01P07

      Total energy in kWh and total water for the works, sent to me to pass on to SKA.

      Who
      Contractor
      Cost
      Team time
    • Deadline set by the scheme: At the handover stage

      Lighting and small power meter readings

      P10P11

      Read and record the lighting and small power sub-meters. The occupancy stage works out a year's use from the difference between these readings and later ones.

      If it slips: P10 is worked out from the handover readings, so missing them puts it at risk. P11 can use any full year within the first two years of occupation.

      Who
      Contractor or facilities team
      Cost
      Team time
    • Deadline set by the scheme: At handover

      As-built energy check

      D66D85

      As-built Energy Use Intensity calculations, with the as-built drawings and equipment schedules checked against the energy model's inputs.

      Who
      Energy modeller
      Cost
      Specialist fee
    • Suggested timing: Certification

      Handover assessment and certificate

      I compile the evidence pack, check actuals against the targets and issue the certificate. SKA says certification takes from a couple of days to a few weeks once the assessment's done, depending on the payment method and how many previews and changes are asked for.

      Who
      Me
  8. RIBA Stage 7: Use: the optional occupancy stage

    Between 12 and 24 months after handover. Mostly a check on what's changed, plus three measures that only exist here.

    • Deadline set by the scheme: A full year of data

      Lighting and small power in use

      P10P11

      A year of metered lighting energy per m², and small power against the CIBSE Guide F benchmarks for the type of space. P11 is in scope on every occupancy assessment.

      Who
      Facilities team
      Cost
      Team time
    • Deadline set by the scheme: If the tenant can buy its own energy

      Renewable energy contracts

      P18

      Electricity backed by REGO certificates or a power purchase agreement with a 100% renewable generator, and gas with RGGO or Biomethane Certificate Scheme backing, with the certificates in the tenant's name.

      Who
      Client
      Cost
      Energy tariff
    • Deadline set by the scheme: 12 months after completion

      Aftercare and post-occupancy evaluation

      D71D69

      Fine-tuning through the first year and a post-occupancy evaluation 12 months after completion and full occupation, against the Soft Landings targets. D69 is checked on whether those targets were met in year one.

      Who
      Design team, contractor and facilities team
      Cost
      Specialist fee
    • Deadline set by the scheme: At the occupancy assessment

      Everything else

      Most measures achieved at handover are achieved by default if nothing's changed, and anything changed or added is assessed again. Some are checked anyway: D85 against measured energy use, D57 against the refrigerant maintenance records, D08 with a site visit, D45 that the user guides are still available, and E29 that its measures are still in place.

      Who
      Me

Where the money goes

My rough guide from projects, not SKA's, and every fit-out is different. The point is that most of the score is effort and timing rather than spend.

Team time

Most of the sixteen: the programme, the workshops, the plans, the records and the user guide. They cost meetings and paperwork, and each one counts towards the share like any other measure.

Specialist fees

The LCA at Stages 2, 4 and 6, and D90 or D47 on top if you opt in. The TM54 energy model. A noise assessment if there's new plant. Lighting energy calculations. Book them at Stage 1 so the Stage 2 work happens on time.

Products, kit and space

ETL-listed plant and lighting, products with EPDs, take-back schemes or certification, sub-meters, leak detection and washroom shut-off, and floor area for cycling and recycling. Specified early, most of these are choices rather than extras.

The expensive mistakes

  • Skipping the Stage 2 audit. D72 is gone, D09 goes with it, and the other resource management measures that lean on the audit get harder.
  • Leaving SKA out of the tender. D07 has to be in front of contractors before they're picked, and adding the rest after award means variations.
  • No lighting sub-meter. P10 comes into scope at occupancy and can't be achieved.
  • Opting in and missing. An opt-in you don't achieve lowers your percentage.
  • Substitutions on site. A cheaper product that doesn't meet the criteria loses a measure you'd already won at design stage.

All 83 measures

What brings each measure into scope, and the stage where the work on it starts. Open a category to see its measures.

Energy

13 measures
  • D01Energy efficient lighting

    In scope when: A general lighting system serving an area over 20 m² is installed or upgraded

    Work starts: Stage 3

  • D02Lighting controllability

    In scope when: New lighting, or existing controls replaced

    Work starts: Stage 3

  • D66Energy modelling

    In scope when: Changes to energy-consuming systems

    Work starts: Stage 1

  • D85Energy Use Intensity

    In scope when: Any change to energy-consuming systems

    Work starts: Stage 4

  • D86Landlord and tenant collaboration

    In scope when: Always

    Work starts: Stage 0

  • E04Energy efficient light fittings

    In scope when: New internal or external light fittings, integrated lamp and fitting only

    Work starts: Stage 3

  • E05Energy efficient heat pumps

    In scope when: New heat pumps of the listed types

    Work starts: Stage 4

  • E08Energy measurement and reporting

    In scope when: Energy-consuming systems installed or modified, unless compliant metering already exists; landlord-controlled central HVAC excluded

    Work starts: Stage 3

  • E29Energy demand reduction

    In scope when: Only if the client chooses to do the study

    Work starts: Stage 1

  • E31Energy efficient ventilation equipment

    In scope when: New ventilation supplying outside air, with plate or rotary heat recovery

    Work starts: Stage 4

  • P10Reduce lighting energy in use

    In scope when: Occupancy stage only, if D01, D02 or E04 were in scope at handover

    Work starts: Stage 3

  • P11Reduce small power energy in use

    In scope when: Occupancy stage only, always

    Work starts: Stage 6

  • P18Zero carbon energy contracts

    In scope when: Occupancy stage only, if the tenant buys its own energy

    Work starts: Stage 7

Environmental health

1 measure
  • D28Healthy internal conditions

    In scope when: Ventilation, heating, cooling or lighting modified

    Work starts: Stage 3

Materials

25 measures
  • D89Embodied carbon assessment

    In scope when: Always, unless the build cost is £500k or below, when it is optional

    Work starts: Stage 1

  • D90Embodied Carbon Intensity

    In scope when: Only if the client chooses to claim Net Zero alignment

    Work starts: Stage 1

  • M03Screed

    In scope when: Any screed specified or installed

    Work starts: Stage 4

  • M04Insulation

    In scope when: Any fire, thermal or acoustic insulation specified or installed

    Work starts: Stage 4

  • M06Joinery

    In scope when: Joinery or bespoke specialist doors

    Work starts: Stage 4

  • M07Raised floor systems

    In scope when: Raised flooring specified and installed

    Work starts: Stage 4

  • M08Partitions

    In scope when: Partitions and wall linings specified, installed or partly modified

    Work starts: Stage 4

  • M10Ceilings

    In scope when: Suspended ceilings, panels or membranes specified, installed or partly modified

    Work starts: Stage 4

  • M11Hard floor covering

    In scope when: Hard flooring specified or installed

    Work starts: Stage 4

  • M12Soft floor covering

    In scope when: Carpet, vinyl, linoleum, rubber and similar, loose rugs included

    Work starts: Stage 4

  • M13Hard wall covering

    In scope when: Tiles, panels, acoustic panels, mirrors and similar

    Work starts: Stage 4

  • M14Paints and coatings

    In scope when: Any paint or coating, primers included

    Work starts: Stage 4

  • M16Wall covering

    In scope when: Wallpaper, films, textile wall coverings or curtains

    Work starts: Stage 4

  • M17Doors

    In scope when: Standard doors, with frames and ironmongery

    Work starts: Stage 4

  • M18Kitchen fittings

    In scope when: Kitchen fittings in tea points or commercial kitchens

    Work starts: Stage 4

  • M19Desks and tables

    In scope when: Loose desks and tables, however they are bought

    Work starts: Stage 4

  • M20Chairs, task seating

    In scope when: Task or meeting chairs, however they are bought

    Work starts: Stage 4

  • M21Storage units

    In scope when: Loose storage, however it is bought

    Work starts: Stage 4

  • M22Other loose furniture

    In scope when: Any other furniture specified, retained, modified, replaced or installed

    Work starts: Stage 4

  • M23Window treatments and curtains

    In scope when: Blinds, drapes or curtains

    Work starts: Stage 4

  • M29Chairs, soft seating

    In scope when: Soft seating, benches or stools, however they are bought

    Work starts: Stage 4

  • M30HVAC equipment

    In scope when: New, relocated or adapted heat pumps, fan coils, air handling or heat recovery units

    Work starts: Stage 4

  • M31Cables, pipes, ducts and lighting controls

    In scope when: Any of the listed items new or reused

    Work starts: Stage 4

  • M32Light fittings

    In scope when: Architectural and integrated light fittings, new or reused

    Work starts: Stage 4

  • M33Decorative and other light fittings

    In scope when: Decorative and other light fittings, new or reused

    Work starts: Stage 4

Ecology

1 measure
  • D20Timber

    In scope when: Any timber, furniture and temporary site timber included

    Work starts: Stage 4

Pollution

4 measures
  • D23Low impact refrigerants

    In scope when: Any new refrigerant used

    Work starts: Stage 4

  • D25Limiting plant noise

    In scope when: New plant that generates external noise

    Work starts: Stage 3

  • D57Refrigerant leak prevention

    In scope when: New or changed refrigerant systems, unless under 3 kg charge or GWP under 5

    Work starts: Stage 4

  • P19Construction water pollution

    In scope when: Plaster, mortar, concrete, screed, paint, liquid adhesives, tiling and similar in the works, or water used to commission services

    Work starts: Stage 4

Project delivery

10 measures
  • D44Project sustainability delivery plan

    In scope when: Always

    Work starts: Stage 4

  • D45Building User Guide

    In scope when: Always

    Work starts: Stage 4

  • D47Whole life carbon assessment

    In scope when: Only if the client chooses it

    Work starts: Stage 1

  • D69Soft Landings: design workshops

    In scope when: Always

    Work starts: Stage 2

  • D70Soft Landings: commissioning, handover and training

    In scope when: Always

    Work starts: Stage 4

  • D71Soft Landings: aftercare

    In scope when: Always

    Work starts: Stage 4

  • D87LCA impact comparison

    In scope when: Only if the client chooses it

    Work starts: Stage 1

  • D88Project delivery programme

    In scope when: Always

    Work starts: Stage 1

  • P01Reduce fit-out energy use

    In scope when: Always

    Work starts: Stage 4

  • P07Reduce fit-out water use

    In scope when: Always

    Work starts: Stage 4

Resource management

21 measures
  • D06Joinery and kitchen fittings

    In scope when: Joinery or kitchen fittings modified or removed

    Work starts: Stage 4

  • D07Site Waste Management Plan

    In scope when: Always

    Work starts: Stage 4

  • D08Recyclable waste storage space

    In scope when: Cat A+ and Cat B fit-outs; optional on Cat A

    Work starts: Stage 3

  • D09Resource Management Plan and Tracker

    In scope when: Always

    Work starts: Stage 1

  • D12Partitions

    In scope when: Existing partitions or linings removed or adjusted, client direct works included

    Work starts: Stage 4

  • D13Ceilings

    In scope when: Existing or new ceilings removed, client direct works included

    Work starts: Stage 4

  • D14Floor coverings

    In scope when: Existing or new floor finishes in the contract

    Work starts: Stage 4

  • D15Desks and tables

    In scope when: Existing desks and tables removed

    Work starts: Stage 4

  • D16Chairs

    In scope when: Existing chairs removed; items containing POPs excluded

    Work starts: Stage 4

  • D17Storage units

    In scope when: Existing storage removed

    Work starts: Stage 4

  • D18Other loose furniture

    In scope when: Other existing loose furniture removed; items containing POPs excluded

    Work starts: Stage 4

  • D34Wall coverings

    In scope when: Existing or new wall coverings in the contract

    Work starts: Stage 4

  • D38Light fittings

    In scope when: Existing light fittings relocated or removed

    Work starts: Stage 4

  • D46Cables, pipes, ducts and lighting controls

    In scope when: Any of the listed items new, relocated or removed

    Work starts: Stage 4

  • D48Doors

    In scope when: Existing doors removed or adjusted

    Work starts: Stage 4

  • D60Design for whole life resource optimisation

    In scope when: Always

    Work starts: Stage 2

  • D68HVAC equipment

    In scope when: Existing or relocated heat pumps, fan coils, heat recovery or air handling units

    Work starts: Stage 4

  • D72Pre-refurbishment audit

    In scope when: Always

    Work starts: Stage 2

  • D73Packaging

    In scope when: Always

    Work starts: Stage 4

  • D74Raised floor systems

    In scope when: Raised floor panels modified or removed

    Work starts: Stage 4

  • D84Fixed asset tagging and register

    In scope when: Always

    Work starts: Stage 4

Transport

4 measures
  • D41Cycle parking

    In scope when: Tenant core or external space with suitable access

    Work starts: Stage 3

  • D42Shower facilities

    In scope when: Enough washroom space, unless adequate showers are already in the building; always with a commercial kitchen, sports facilities or hot or grimy work

    Work starts: Stage 3

  • D43Cyclist lockers

    In scope when: Enough core space, unless enough lockers are already in the building

    Work starts: Stage 3

  • D59Construction phase transport CO₂

    In scope when: Always

    Work starts: Stage 4

Water

4 measures
  • E14Efficient taps

    In scope when: Taps installed or replaced

    Work starts: Stage 4

  • E17Water measurement and reporting

    In scope when: Any work to the water supply, even one tap

    Work starts: Stage 3

  • E19Sanitary supply shut-off

    In scope when: Water supply installed or modified

    Work starts: Stage 4

  • E20Water leak detection

    In scope when: Water supply installed or modified

    Work starts: Stage 4

Scoping wording is shortened from the GPM's. I check every project's scope against the full scheme document.

SKA Offices 2.0 roadmap FAQs

Which measures depend on others?

Several. D09, the resource tracker, can only be achieved if D72, D60 and D07 are achieved, and D84 too on projects over £2m. D85 needs the D66 energy model. D90 needs the D89 LCA, including the Stage 6 actuals report. SKA's Net Zero aligned certificate needs both D85 and D90.

So one missed early deadline can cost two measures, which is why the audit and the first resource workshop matter more than they look.

Want me to scope yours? Get in touch.

Can we scope a measure out to protect the score?

Not one that applies. Measures come into scope by what the works include, and SKA audits its assessors on getting the scoping right.

The real choices are the opt-ins: D47, D87, D90 and E29, plus D89 at £500k or less and D08 on a Cat A fit-out. Each one you take on adds a measure to the count, so it only helps if you achieve it.

We're already at Stage 3 or 4. Is it too late?

Not for a certificate, but expect some losses. The D72 audit and the first D60 workshop both belong to Concept Design, and D09 can't be achieved without them. On £4m and over, D89 needed a Stage 2 LCA report. D88 should have been set up in Stage 1, and D86 depends on whether the lease is still being negotiated. D90 needs Stage 2 and 4 LCA results, so think hard before opting in now.

Most of the score is still open, though. The specifications, the tender documents and the site evidence carry far more measures than the early stages do.

Tell me where you are and I'll tell you what's still achievable.

What does the Net Zero aligned certificate need?

D85 Energy Use Intensity and D90 Embodied Carbon Intensity, both achieved. D90 is an opt-in, needs the D89 LCA at Stages 2 and 4 and the Stage 6 actuals report, and has to meet the UK Net Zero Carbon Buildings Standard upfront limit for the year you start on site.

The certificate comes at whatever rating you achieve, and it's SKA's own. It has no official link to certification under the UK Net Zero Carbon Buildings Standard.

How long after handover do we get the certificate?

SKA says the certification process takes between a couple of days and a few weeks once the assessor has completed the handover assessment, depending on the payment method and how many previews and changes are asked for.

The assessment itself can't finish until the evidence pack is complete, so collect it as you go.

Planning a handover date? Get in touch.

Services

Specialist capacity, without the headcount

Consultancy, contractor or in-house team with more certification work than people to deliver it? I plug in for as long as the work exists across commercial fit-outs and refurbishments. You keep the client. I do the certification work.

  • Licensed Assessor and AP

    BREEAM services

    Licensed Assessor for UK New Construction, and AP (Design and Site) from concept design to site.

  • SKA Assessor

    SKA Rating services

    Fit-out assessments, from scoping the measures to issuing the certificate.

  • WELL AP

    WELL services

    Route, scorecard and documentation, with the submission managed through IWBI review.

  • Fitwel Ambassador

    Fitwel services

    Scorecard set-up, evidence and submission, for new and existing buildings.

  • WiredScore AP

    WiredScore services

    Gap analysis, target level, evidence pack and improvement advice.

  • ActiveScore and ModeScore AP

    ActiveScore services

    Submission, score modelling and the improvements worth making.

How I workUK Whole Life Carbon MapFAQs

George Michael Kakas

Got a SKA project that needs a pair of hands?

Email or call me. Tell me what the project is, where it's up to and which scheme it's after, and attach drawings, a programme or a scope of works if you have them.

George Michael Kakas

Owner at Welscape